JJM 2021-22 - Setting up/ Upgradation/ Operation of Laboratories - Setting up of new Sub District Laboratory at Adimali

Project JJM 2021-22 - Setting up/ Upgradation/ Operation of Laboratories - Setting up of new Sub District Laboratory at Adimali
Project Code IDKJJM09218467
Type Main project
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-01
Description Setting up/ Upgradation/ Operation of Laboratories - Setting up of new Sub District Laboratory at Adimali
Status Completed
District Idukki
Executing Office Idukki QC Sn
AS Amount (Rs) 838600000
AS Number 489/2021/WRD
TS Amount (Rs) 3300000
TS Number TS/2021-2022/2021/34263
Total Bill Submitted (Rs) 2013795
Total Bill Paid (Rs) 1833988
Population Benefitted 400000
Capacity in MLD 0.00
Actual Project Completion Date 28 Apr 2022
Coverage Setting up of New sub district lab at Adimaly in Idukki district .
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 JJM 2021-22 - Setting up/ Upgradation/ Operation of Laboratories - Setting up of new Sub District Laboratory at Adimali Idukki QC Sn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
19 Jul 2022 Work completed ,Final bill under preparation. Idukki QCDL - AE
19 Jul 2022 Work completed ,Final bill under preparation. Idukki QCDL - AE
25 Mar 2022 90% work completed .Finishing works in progress. Idukki QCDL - AE
25 Feb 2022 69% work completed. Idukki QCDL - AE
03 Feb 2022 Work in progress 60% Completed . Idukki QCDL - AE

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 24/11/2021
Scheduled date of Completion of the Project 21 Feb 2022
Expected date of Completion 28/02/2022

Processing Dates

AS Date 18 Sep 2021
TS Date 05 Nov 2022

Other details

Project Officers View