Project | JJM - Cherpu Grama Panchayath-Providing service water connections and Extension of Pipelines at various places for full coverage of FHTC -BALANCE WORK |
---|---|
Project Code | TCRJJM08203896P8 |
Type | Package |
Main Project | JJM-2020-21 - Cherpu Grama Panchayath - SPAN Urakam and adjoining villages - Leak rectification works of GL tank at Pallisserykunnu & Providing 3794 nos of service water connections . |
Funding Agency | JJM |
Category | JJM |
Type of scheme | Water Supply |
Scheme | 4215-01-102-92-02 |
Description | Providing FHTC -500 Supply and laying of PVC pipe - 50mm PVC- 990m, 63mmPVC - 500m, 75mm PVC-1400m |
Status | On-going |
District | Thrissur |
Executing Office | Cherpu PH Sn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 10000000 |
TS Number | WRD/KWA-CE(CR)/EST_TS/22380/2023_26_1_1 |
Technical specification | |
Contractor | M.A.Jose (Mob: 9447529314) |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 22/01/2024 |
---|---|
Scheduled date of Completion as per agreement | 29 Apr 2024 |
Expected date of Completion | 29/04/2024 |
TS Date | 05 Jan 2024 |
---|---|
Estimate Approval | 05 Jan 2024 |
NIT Approval | 05 Jan 2024 |
Tender Closing | 12 Jan 2024 |
Technichal Pre-Qualification | 15 Jan 2024 |
Price bid opening | 15 Jan 2024 |
Workorder Date | 22 Jan 2024 |
---|---|
NA | 29 Jan 2024 |
Cherpu AE |
Date: 25/06/2024 |
Work in progress | 58% Completed
No work on site today.
Cherpu AE |
Date: 24/06/2024 |
Work in progress | 58% Completed
No work on site today.