KIIFB-2016-17-WRD002-09- Augmentation of WSS to Kottayam Municipality, Package II-Supplying,laying,testing and commissioning of various sizes of (600 mm to 150 mm) DI K9 pipes,710 mm HDPE pipes and distribution system at various places and supply and erection of clear water pumpsets at KWA campus pump house

Project KIIFB-2016-17-WRD002-09- Augmentation of WSS to Kottayam Municipality, Package II-Supplying,laying,testing and commissioning of various sizes of (600 mm to 150 mm) DI K9 pipes,710 mm HDPE pipes and distribution system at various places and supply and erection of clear water pumpsets at KWA campus pump house
Project Code KTMKIIFB0117545P2
Type Package
Main Project KIIFB-2016-17- WRD-002-09 Augmentation of UWSS to Kottayam Municipality
Funding Agency KIIFB
Category KIIFB
Type of scheme Water Supply
Scheme KIIFB
Description Supplying,laying,testing and commissioning of various sizes of (600 mm to 150 mm) DI K9 pipes,710 mm HDPE pipes and distribution system at various places and supply and erection of clear water pumpsets at KWA campus pump house
Status On-going
District Kottayam
Executing Office Kottayam Project Dn
Agreement Number
Agreement Date
TS Amount (Rs) 500000000
TS Number KWA/CE(SR)/17/2016-17
Technical specification 400 mm DI K9 pipes from Mosco Junction to Incherikunnu OHSR 300 mm DI K9 and 160 mm PVC pipes from Collectorate to Kanjikuzhi junction on LHS & RHS 600 mm DI K9 from OHSR at KWA campus to Mariyapally OHSR
Contractor Chicago Constructions International Pvt Ltd (Mob: 9447111906)

No project review have been added to this project

Reported Issues

Issue date Solved On Action Taken On Category Description Comments Issue Status
22 Sep 2021 Pending Pending Approval/Permissions Related (from other departments excluding road cut permission and land related) Road cutting for laying pipes on NH 183(KK Road & M Road) denied by Regional Office,MoRTH ,Trivandrum. No comments available. Pending

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 27/11/2020
Scheduled date of Completion as per agreement 16 Feb 2022
Expected date of Completion 16/12/2022

Processing Dates

TS Date 23 Jan 2017
Estimate Approval 02 Aug 2018
NIT Approval 02 Aug 2018
Tender Closing 03 Jul 2018
Technichal Pre-Qualification 07 Jul 2018
Price bid opening 07 Jul 2018

Approval Dates

Workorder Date 29 Jun 2020
NA 17 Aug 2020

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Kottayam Proj Dn AE4
Date: 11/04/2024

Work in progress | 66% Completed

Work Fore closed and final bill submitted. .

Kottayam Proj Dn AE4
Date: 10/04/2024

Work in progress | 66% Completed

Work Fore closed and final bill submitted. .