| Project | KIIFB 2017-18- Drinking water project in Ettumanoor Municipality Package -1 |
|---|---|
| Project Code | KTMKIIFB0619525P1 |
| Type | Package |
| Main Project | KIIFB 2017-18- Drinking water project in Ettumanoor Municipality |
| Funding Agency | KIIFB |
| Category | KIIFB WATER SUPPLY SCHEME | Type of scheme | Water Supply |
| Description | Package-I. Raw water pumping main from well to WTP,Raw water pumpset, Powerenhancement, leading pipe, 22mld WTP, Construction of OHSR at WTP site, CWGM to Carithas,Boosting station Ettumanoor, CWPM, distribution main etc. |
| Status | On-going |
| District | Kottayam |
| Executing Office | Kottayam Project Dn |
| TS Amount (Rs) | |
| TS Number | |
| Technical specification | WTP- 22mld, RWPM-600mm DI K-9 4600m, CWPM-250mm DI-9, CWGM- 30mm DI K-9, Raw water pumpset- V/T, CWP/S-C/F, 16LL OHSR,20LL GLSum, Leading pipe-500mm DI K-9 |
Project Progress Status |
Project Progress Status |
| Date of start of Package | Date is not specified |
|---|---|
| Scheduled date of Completion as per agreement | Date is not specified |
| Expected date of Completion | 31/03/2023 |
| AS Date | 21 Jun 2019 |
|---|
| AE3 ktm |
| Date: 02/06/2021 |
Work has started | 0% Completed
letter received collectorate seeking opinion about SIA report.
| AE3 ktm |
| Date: 26/05/2021 |
Work has started | 0% Completed
Social Impact Assessment committee Report submitted to the District Collector .