Project | KIIFB-WSS to Perinadu and Athikkayam Villages-Phase II-Package II |
---|---|
Project Code | PTAKIIFB0117573P2 |
Type | Package |
Main Project | KIIFB_WSS to Perinadu and Athikkayam Villages-Phase II |
Funding Agency | KIIFB |
Category | KIIFB |
Type of scheme | Water Supply |
Scheme | KIIFB |
Description | This package includes laying distribution systen in zone 8to 11, Supplying and Laying Clear Water Gravity Main from Kottupara GL Tank to Mampara GL Tank,Supplying and Laying Clear Water Pumping Main from Treatment Plant to Pancharamukku Sump cum Pump House,Supplying and Laying Clear Water Pumping Main from Sump near Treatment Plant to Sump at Mundamala Low Level,Supplying and Laying Clear Water Pumping Main Sump at Mundamala Low Level to GLSR at Mundamala High Level,Supplying and Laying Clear Water Pumping Main from Sump at Pancharamukk to Chembanmudi GLSR,Construction of Pump House at Mundamala Low Level,Construction of 0.50 LL GLSR at Mundamala Top. |
Status | On-going |
District | Pathanamthitta |
Executing Office | Adoor Project Dn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 137800000 |
TS Number | TS/2018-2019/2018/1942 Dated: 26-02-2019 |
Technical specification | zone 8to 11, Supplying and Laying Clear Water Gravity Main from Kottupara GL Tank to Mampara GL Tank,Supplying and Laying Clear Water Pumping Main from Treatment Plant to Pancharamukku Sump cum Pump House,Supplying and Laying Clear Water Pumping Main from Sump near Treatment Plant to Sump at Mundamala Low Level,Supplying and Laying Clear Water Pumping Main Sump at Mundamala Low Level to GLSR at Mundamala High Level,Supplying and Laying Clear Water Pumping Main from Sump at Pancharamukk to Chembanmudi GLSR,Construction of Pump House at Mundamala Low Level,Construction of 0.50 LL GLSR at Mundamala Top. |
Contractor | Biju Augustine (Mob: 9447060360) |
Issue date | Solved On | Action Taken On | Category | Description | Comments | Issue Status |
---|---|---|---|---|---|---|
09 Feb 2022 | Pending | 09 Feb 2022 | Approval/Permissions Related (from other departments excluding road cut permission and land related) | Delay in obtaining estimate from PWD for road restoration of DLP road. | No comments added. | Action Taken |
01 Feb 2022 | 02 Feb 2022 | Pending | Approval/Permissions Related (from other departments excluding road cut permission and land related) | Estimate from PWD requested for restoration of BMBC road near Athikkayam bridge. Bank guarantee remitted. | Bank guarantee remitted | Solved |
27 Jan 2022 | Pending | 29 Jan 2022 | Road Cut Related Risk | Copy of Bank guarantee for road restoration uploaded to ROW. Quantity of concrete of anchor block and road restoration of panchayat roads achieved, no provision for completing anchor block and road restoration. | No comments added. | Action Taken |
12 Jan 2022 | Pending | 01 Feb 2022 | Road Cut Related Risk | Bank guarantee remitted to PWD for road cutting sanction in Athikkayam- Perunad road | No comments added. | Action Taken |
15 Dec 2021 | 12 Jan 2022 | Pending | Road Cut Related Risk | Bank guarantee to be remitted to PWD Roads Division Pathanamthitta by FM KWA from centage charge of KIIFB. | Bank guarantee remitted to PWD | Solved |
01 Nov 2021 | Pending | 01 Feb 2022 | Road Cut Related Risk | The PWD has informed that the 275 meter long road cutting permission near the Athikkayam bridge on the Perunad-Athikkayam road will be allowed only after the sabarimala season as the security deposit has not been paid. TOC 24 .12 .2021 | No comments added. | Action Taken |
14 Apr 2021 | 28 Dec 2022 | Pending | Land Related Risk | 100 mm DI Pumping main from Pancharamukku sump to 100 mm DI Pumping main from Pancharamukku sump to Chembanmudy GLSR is to be laid through a private land boundary. No alternate road for laying. If lay through road required more length, no provision in this work GLSR in this work to be laid through a private land boundary. No alternate road for laying. | Obtained oral permission from land owner to lay pipes. | Solved |
13 Apr 2021 | Pending | 20 Jan 2022 | Road Cut Related Risk | For road cutting near to Athikkayam bridge for laying pumping main from WTP to Pancharamukku road restoration estimate received from PWD and requested to remit security amount. Fund for Road restoration security amount is to be remitted to PWD for getting road cutting permission | No comments added. | Action Taken |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 19/11/2019 |
---|---|
Scheduled date of Completion as per agreement | 30 Mar 2022 |
Expected date of Completion | 30/03/2022 |
TS Date | 26 Feb 2019 |
---|---|
Estimate Approval | 26 Feb 2019 |
NIT Approval | 08 Apr 2019 |
Tender Closing | 08 Apr 2019 |
Technichal Pre-Qualification | 25 May 2019 |
Price bid opening | 10 Apr 2019 |
Workorder Date | 29 Sep 2019 |
---|---|
NA | 24 Oct 2019 |
Adoor Project Dn AE 4 |
Date: 31/03/2022 |
Work has been completed | 100% Completed
Completed .
Adoor Project Dn AE 4 |
Date: 30/03/2022 |
Work in progress | 98% Completed
In Phase II package II all works are in progress and completed 13730.15 m out of 14000 m CWPM& CWGM and 41655 m out of 44915 m distribution. Pipe laying work is in progress and nearing completion. Construction of GLSR and compound wall at Mundamala HL completed. Construction of pump house at Mundamala LL and compound wall Completed. Interconnection and laying of pipeline works and maintenance of existing tanks are in progress. Quantity of concrete of anchor block and road restoration of panchayath roads achieved, no provision for completing anchor block and road restoration. Remitted bank guarantee and uploaded in ROW and in physical form to PWD. Requested estimate from PWD for arranging restoration of BMBC road. .