Project | JAL JEEVAN MISSION 2021-22- PHASE II - PROVIDING FUNCTIONAL HOUSE HOLD TAP CONNECTION BY AUGMENTATION AND EXTENSION OF EXISTING WSS IN MAVOOR GRAMA PANCHAYATH IN KOZHIKODE DISTRICT |
---|---|
Project Code | CLTJJM09219060P1 |
Type | Package |
Main Project | JAL JEEVAN MISSION 2021-22- PHASE II - PROVIDING FUNCTIONAL HOUSE HOLD TAP CONNECTION BY AUGMENTATION AND EXTENSION OF EXISTING WSS IN MAVOOR GRAMA PANCHAYATH IN KOZHIKODE DISTRICT |
Funding Agency | JJM |
Category | JJM |
Type of scheme | Water Supply |
Scheme | 4215-01-102-92-02 |
Description | Mavoor grama panchayath falls under the scheme coverage area of comprehensive scheme 72 MLD capacity of Calicut WSS thus a Multi village scheme. The treatment plant is 72 MLD capacity situated at Koolimadu. The service reservoir of Mavoor Panchayath is 7.5 lakhs litre capacity OH tank . Presently , as per JJM google spread sheet details of Panchayatath wise FHTC ,there are 6545 Nos. of households in Mavoor grama Panchayath , out of which 2546 no.s of house holds are already having FHTCs . The Phase-I Jal Jeevan mission project for Mavoor Grama Panchayath, for providing FHTCs by retrofitting and augmentation of existing water supply system has been completed satisfactorily . In PhaseII Jal Jeevan mission project for Mavoor Grama Panchayath, it is envisaged to provide balance 3999 FHTCs to households by augmentation and extension of existing water supply system. Distribution main lines are adopted as per the design of PPD wing of KWA. Total estimate amount of Phase-II Jal Jeevan mission project for Mavoor Grama Panchayath is Rs 2800.00 lakhs .Some areas of Mavoor Panchayath is higher than the existing OH tank level and for 100% coverage sumps and boosting station are provided in this estimate . In this estimate it includes the supply of 500mm DI K9 pipes for a length of 200m, 400mm DI K9 pipes for a length of 2220m, 350mm DI K9 pipes for a length of 2143m, 300mm DI K9 pipes for a length of 2935m, 250mm DI K9 pipes for a length of 2570m, 200mm DI K9 pipes for a length of 2929m, 160mm PE (10 Kg/cm2) Pipes for a length of 3016m , 140mm PE (10Kg/cm2) - 4945 m, 110mm PE (10Kg/cm2) - 3223 m, 90mm PE (10Kg/cm2) - 24200m, 75mm PE (10Kg/cm2) - 37997 m,150mm GI pipes for a length of 100m, 125mm GI pipes for a length of 60m, 100 mm GI pipes for a length of 50m , 80 mm GI pipes for a length of 800 m ,65 mm GI pipes for a length of 1500 m , and 20mm PE pipes for a additional length of 54540m for the extension of pipelines and for providing FHTCs . |
Status | On-going |
District | Kozhikkode |
Executing Office | Malapparamba RWS Sn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 271000000 |
TS Number | 15330/2021-2022 |
Technical specification | 1)AS No.GO(Rt) No.489/2021/WRD Dated:18-09-2021 Rs. 280000000.00 2)TS No.15330/2021-2022 dated 14-12-2021 Rs.2710 Lakhs |
Contractor | MIDLAND ENGINEERING (Mob: 9447136631) |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 20/04/2022 |
---|---|
Scheduled date of Completion as per agreement | 28 Feb 2023 |
Expected date of Completion | 31/05/2023 |
TS Date | 14 Dec 2021 |
---|---|
Estimate Approval | 14 Dec 2021 |
NIT Approval | 17 Dec 2021 |
Tender Closing | 10 Jan 2022 |
Price bid opening | 13 Jan 2022 |
Workorder Date | 16 Feb 2022 |
---|---|
NA | 20 Apr 2022 |
Malaparamba RWS Sn - AE |
Date: 29/06/2024 |
Work in progress | 94% Completed
90mm pipe laying Ayamkulam (ward 16) Depth 50cm.
Malaparamba RWS Sn - AE |
Date: 25/06/2024 |
Work in progress | 94% Completed
I/c Theerthakunn OH tank to sump - at ward 6.