JAL JEEVAN MISSION 2021-22- PHASE II - PROVIDING FUNCTIONAL HOUSE HOLD TAP CONNECTION BY AUGMENTATION AND EXTENSION OF EXISTING WSS IN MAVOOR GRAMA PANCHAYATH IN KOZHIKODE DISTRICT

Project JAL JEEVAN MISSION 2021-22- PHASE II - PROVIDING FUNCTIONAL HOUSE HOLD TAP CONNECTION BY AUGMENTATION AND EXTENSION OF EXISTING WSS IN MAVOOR GRAMA PANCHAYATH IN KOZHIKODE DISTRICT
Project Code CLTJJM09219060P1
Type Package
Main Project JAL JEEVAN MISSION 2021-22- PHASE II - PROVIDING FUNCTIONAL HOUSE HOLD TAP CONNECTION BY AUGMENTATION AND EXTENSION OF EXISTING WSS IN MAVOOR GRAMA PANCHAYATH IN KOZHIKODE DISTRICT
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description Mavoor grama panchayath falls under the scheme coverage area of comprehensive scheme 72 MLD capacity of Calicut WSS thus a Multi village scheme. The treatment plant is 72 MLD capacity situated at Koolimadu. The service reservoir of Mavoor Panchayath is 7.5 lakhs litre capacity OH tank . Presently , as per JJM google spread sheet details of Panchayatath wise FHTC ,there are 6545 Nos. of households in Mavoor grama Panchayath , out of which 2546 no.s of house holds are already having FHTCs . The Phase-I Jal Jeevan mission project for Mavoor Grama Panchayath, for providing FHTCs by retrofitting and augmentation of existing water supply system has been completed satisfactorily . In PhaseII Jal Jeevan mission project for Mavoor Grama Panchayath, it is envisaged to provide balance 3999 FHTCs to households by augmentation and extension of existing water supply system. Distribution main lines are adopted as per the design of PPD wing of KWA. Total estimate amount of Phase-II Jal Jeevan mission project for Mavoor Grama Panchayath is Rs 2800.00 lakhs .Some areas of Mavoor Panchayath is higher than the existing OH tank level and for 100% coverage sumps and boosting station are provided in this estimate . In this estimate it includes the supply of 500mm DI K9 pipes for a length of 200m, 400mm DI K9 pipes for a length of 2220m, 350mm DI K9 pipes for a length of 2143m, 300mm DI K9 pipes for a length of 2935m, 250mm DI K9 pipes for a length of 2570m, 200mm DI K9 pipes for a length of 2929m, 160mm PE (10 Kg/cm2) Pipes for a length of 3016m , 140mm PE (10Kg/cm2) - 4945 m, 110mm PE (10Kg/cm2) - 3223 m, 90mm PE (10Kg/cm2) - 24200m, 75mm PE (10Kg/cm2) - 37997 m,150mm GI pipes for a length of 100m, 125mm GI pipes for a length of 60m, 100 mm GI pipes for a length of 50m , 80 mm GI pipes for a length of 800 m ,65 mm GI pipes for a length of 1500 m , and 20mm PE pipes for a additional length of 54540m for the extension of pipelines and for providing FHTCs .
Status On-going
District Kozhikkode
Executing Office Malapparamba RWS Sn
Agreement Number
Agreement Date
TS Amount (Rs) 271000000
TS Number 15330/2021-2022
Technical specification 1)AS No.GO(Rt) No.489/2021/WRD Dated:18-09-2021 Rs. 280000000.00 2)TS No.15330/2021-2022 dated 14-12-2021 Rs.2710 Lakhs
Contractor MIDLAND ENGINEERING (Mob: 9447136631)

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 20/04/2022
Scheduled date of Completion as per agreement 28 Feb 2023
Expected date of Completion 31/05/2023

Processing Dates

TS Date 14 Dec 2021
Estimate Approval 14 Dec 2021
NIT Approval 17 Dec 2021
Tender Closing 10 Jan 2022
Price bid opening 13 Jan 2022

Approval Dates

Workorder Date 16 Feb 2022
NA 20 Apr 2022

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Malaparamba RWS Sn - AE
Date: 29/06/2024

Work in progress | 94% Completed

90mm pipe laying Ayamkulam (ward 16) Depth 50cm.

Malaparamba RWS Sn - AE
Date: 25/06/2024

Work in progress | 94% Completed

I/c Theerthakunn OH tank to sump - at ward 6.