JAL JEEVAN MISSION 2021-22- PHASE II - PROVIDING FUNCTIONAL HOUSE HOLD TAP CONNECTION BY AUGMENTATION AND EXTENSION OF EXISTING WSS IN MAVOOR GRAMA PANCHAYATH IN KOZHIKODE DISTRICT

Project JAL JEEVAN MISSION 2021-22- PHASE II - PROVIDING FUNCTIONAL HOUSE HOLD TAP CONNECTION BY AUGMENTATION AND EXTENSION OF EXISTING WSS IN MAVOOR GRAMA PANCHAYATH IN KOZHIKODE DISTRICT
Project Code CLTJJM09219060
Type Main project
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description Mavoor grama panchayath falls under the scheme coverage area of comprehensive scheme 72 MLD capacity of Calicut WSS thus a Multi village scheme. The treatment plant is 72 MLD capacity situated at Koolimadu. The service reservoir of Mavoor Panchayath is 7.5 lakhs litre capacity OH tank . Presently , as per JJM google spread sheet details of Panchayatath wise FHTC ,there are 6545 Nos. of households in Mavoor grama Panchayath , out of which 2546 no.s of house holds are already having FHTCs . The Phase-I Jal Jeevan mission project for Mavoor Grama Panchayath, for providing FHTCs by retrofitting and augmentation of existing water supply system has been completed satisfactorily . In PhaseII Jal Jeevan mission project for Mavoor Grama Panchayath, it is envisaged to provide balance 3999 FHTCs to households by augmentation and extension of existing water supply system. Distribution main lines are adopted as per the design of PPD wing of KWA. Total estimate amount of Phase-II Jal Jeevan mission project for Mavoor Grama Panchayath is Rs 2800.00 lakhs .Some areas of Mavoor Panchayath is higher than the existing OH tank level and for 100% coverage sumps and boosting station are provided in this estimate . In this estimate it includes the supply of 500mm DI K9 pipes for a length of 200m, 400mm DI K9 pipes for a length of 2220m, 350mm DI K9 pipes for a length of 2143m, 300mm DI K9 pipes for a length of 2935m, 250mm DI K9 pipes for a length of 2570m, 200mm DI K9 pipes for a length of 2929m, 160mm PE (10 Kg/cm2) Pipes for a length of 3016m , 140mm PE (10Kg/cm2) - 4945 m, 110mm PE (10Kg/cm2) - 3223 m, 90mm PE (10Kg/cm2) - 24200m, 75mm PE (10Kg/cm2) - 37997 m,150mm GI pipes for a length of 100m, 125mm GI pipes for a length of 60m, 100 mm GI pipes for a length of 50m , 80 mm GI pipes for a length of 800 m ,65 mm GI pipes for a length of 1500 m , and 20mm PE pipes for a additional length of 54540m for the extension of pipelines and for providing FHTCs . In this estimate the items for demolishing bituminous surface/ cement concrete roads & footpath, demolishing stone rubble , rubble paving, fill the trenches with quarry muck & WMM and to restore the roads & footpaths with cement concrete, interconnection works,construction of valve chamber are included. Different sizes of valves (80mm,100mm,150mm ) , Air valves and PRV s for regulating/controlling the flow also included in this estimate . The rate of GI pipes are taken from the DSR and DLPC rates approved
Status On-going
District Kozhikkode
Executing Office Kozhikode PH Dn
AS Amount (Rs) 280000000
AS Number GO(Rt) No.489/2021/WRD
TS Amount (Rs) 271000000
TS Number 15330/2021-2022
Total Bill Submitted (Rs) 225291193
Total Bill Paid (Rs) 225291193
Population Benefitted 19995
Capacity in MLD 72.00
Actual Project Completion Date 31 May 2023
Coverage . In this estimate it includes the supply of 500mm DI K9 pipes for a length of 200m, 400mm DI K9 pipes for a length of 2220m, 350mm DI K9 pipes for a length of 2143m, 300mm DI K9 pipes for a length of 2935m, 250mm DI K9 pipes for a length of 2570m, 200mm DI K9 pipes for a length of 2929m, 160mm PE (10 Kg/cm2) Pipes for a length of 3016m ,140mm PE (10Kg/cm2) - 4945 m, 110mm PE (10Kg/cm2) - 3223 m, 90mm PE (10Kg/cm2) - 24200m, 75mm PE (10Kg/cm2) - 37997 m,150mm GI pipes for a length of 100m, 125mm GI pipes for a length of 60m, 100 mm GI pipes for a length of 50m , 80 mm GI pipes for a length of 800 m ,65 mm GI pipes for a length of 1500 m , and 20mm PE pipes for a additional length of 54540m for the extension of pipelines and for providing FHTCs
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 JAL JEEVAN MISSION 2021-22- PHASE II - PROVIDING FUNCTIONAL HOUSE HOLD TAP CONNECTION BY AUGMENTATION AND EXTENSION OF EXISTING WSS IN MAVOOR GRAMA PANCHAYATH IN KOZHIKODE DISTRICT Malapparamba RWS Sn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
30 May 2024 pipe laying work in progress Malaparamba RWS Sn - AE
16 May 2024 pipe laying work geo tagging, tank and sump work in progress Malaparamba RWS Sn - AE
19 Apr 2024 pipe laying work geo tagging, tank and sump work in progress Malaparamba RWS Sn - AE
09 Apr 2024 pipe laying work geo tagging, tank and sump work in progress Malaparamba RWS Sn - AE
03 Apr 2024 pipe laying work geo tagging, tank and sump work in progress Malaparamba RWS Sn - AE

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 19/02/2022
Scheduled date of Completion of the Project 28 Feb 2023
Expected date of Completion 31/03/2023

Processing Dates

AS Date 18 Sep 2021
TS Date 14 Dec 2021

Other details

Project Officers View