JAL JEEVAN MISSION 2021-22 - Phase II - CWSS to Chavara & Panmana (Jalanidhi Scheme) - Providing FHTCs, Extension of Pipe line ,Construction of Tube well, Supply and erection of pump sets with allied works, Supply and installation of Bulk Water Meters with meter chambers etc. in Panmana Grama Panchayat.
Project |
JAL JEEVAN MISSION 2021-22 - Phase II - CWSS to Chavara & Panmana (Jalanidhi Scheme) - Providing FHTCs, Extension of Pipe line ,Construction of Tube well, Supply and erection of pump sets with allied works, Supply and installation of Bulk Water Meters with meter chambers etc. in Panmana Grama Panchayat. |
Project Code |
KLMJJM092110690P1 |
Type |
Package |
Main Project |
JAL JEEVAN MISSION 2021-22 - Phase II - CWSS to Chavara & Panmana (Jalanidhi Scheme) - Providing FHTCs, Extension of Pipe line ,Construction of Tube well, Supply and erection of pump sets with allied works, Supply and installation of Bulk Water Meters with meter chambers etc. in Panmana Grama Panchayat.
|
Funding Agency |
JJM |
Category |
JJM |
Type of scheme |
Water Supply |
Scheme |
4215-01-102-92-02 |
Description |
AL JEEVAN MISSION 2021-22 - Phase II - CWSS to Chavara & Panmana (Jalanidhi Scheme) - Providing FHTCs, Extension of Pipe line ,Construction of Tube well, Supply and erection of pump sets with allied works, Supply and installation of Bulk Water Meters with meter chambers etc. in Panmana Grama Panchayat. |
Status |
On-going |
District |
Kollam |
Executing Office |
Chavara PH Sn |
Agreement Number |
|
Agreement Date |
|
TS Amount (Rs) |
68200000 |
TS Number |
13462/2021-2022 |
Technical specification |
Phase II - CWSS to Chavara & Panmana (Jalanidhi Scheme) - Providing FHTCs, Extension of Pipe line ,Construction of Tube well, Supply and erection of pump sets with allied works, Supply and installation of Bulk Water Meters with meter chambers etc. in Panmana Grama Panchayat. |
No project review have been added to this project
Project Progress Status
|
Project Progress Status
|
Duration & Sanction dates
Date of start of Package |
10/03/2022 |
Scheduled date of Completion as per agreement |
09 Mar 2023 |
Expected date of Completion |
09/03/2023 |
Processing Dates
TS Date |
19 Nov 2021 |
Estimate Approval |
19 Nov 2021 |
NIT Approval |
21 Dec 2021 |
Tender Closing |
13 Jan 2022 |
Technichal Pre-Qualification |
13 Jan 2022 |
Price bid opening |
15 Jan 2022 |
Approval Dates
Workorder Date |
16 Feb 2022 |
NA |
10 Mar 2022 |
Other details
Project Schedule |
View |
Project Components |
View |
Project Officers |
View |
Chavara AE |
Date: 29/06/2024 |
Work in progress | 86% Completed
18950m laying completed,Out of 2864 connections 2195 connections completed. Panchayath not handed over list of balance connections even after repeated letters. 16 th and part bill submitted .
Chavara AE |
Date: 26/06/2024 |
Work in progress | 85% Completed
18950m laying completed, 2195 connections completed, 16 th and part bill submitted.