JAL JEEVAN MISSION 2021-22 - Phase II - CWSS to Chavara & Panmana (Jalanidhi Scheme) - Providing FHTCs, Extension of Pipe line ,Construction of Tube well, Supply and erection of pump sets with allied works, Supply and installation of Bulk Water Meters with meter chambers etc. in Panmana Grama Panchayat.

Project JAL JEEVAN MISSION 2021-22 - Phase II - CWSS to Chavara & Panmana (Jalanidhi Scheme) - Providing FHTCs, Extension of Pipe line ,Construction of Tube well, Supply and erection of pump sets with allied works, Supply and installation of Bulk Water Meters with meter chambers etc. in Panmana Grama Panchayat.
Project Code KLMJJM092110690P1
Type Package
Main Project JAL JEEVAN MISSION 2021-22 - Phase II - CWSS to Chavara & Panmana (Jalanidhi Scheme) - Providing FHTCs, Extension of Pipe line ,Construction of Tube well, Supply and erection of pump sets with allied works, Supply and installation of Bulk Water Meters with meter chambers etc. in Panmana Grama Panchayat.
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description AL JEEVAN MISSION 2021-22 - Phase II - CWSS to Chavara & Panmana (Jalanidhi Scheme) - Providing FHTCs, Extension of Pipe line ,Construction of Tube well, Supply and erection of pump sets with allied works, Supply and installation of Bulk Water Meters with meter chambers etc. in Panmana Grama Panchayat.
Status On-going
District Kollam
Executing Office Chavara PH Sn
Agreement Number
Agreement Date
TS Amount (Rs) 68200000
TS Number 13462/2021-2022
Technical specification Phase II - CWSS to Chavara & Panmana (Jalanidhi Scheme) - Providing FHTCs, Extension of Pipe line ,Construction of Tube well, Supply and erection of pump sets with allied works, Supply and installation of Bulk Water Meters with meter chambers etc. in Panmana Grama Panchayat.

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 10/03/2022
Scheduled date of Completion as per agreement 09 Mar 2023
Expected date of Completion 09/03/2023

Processing Dates

TS Date 19 Nov 2021
Estimate Approval 19 Nov 2021
NIT Approval 21 Dec 2021
Tender Closing 13 Jan 2022
Technichal Pre-Qualification 13 Jan 2022
Price bid opening 15 Jan 2022

Approval Dates

Workorder Date 16 Feb 2022
NA 10 Mar 2022

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Chavara AE
Date: 29/06/2024

Work in progress | 86% Completed

18950m laying completed,Out of 2864 connections 2195 connections completed. Panchayath not handed over list of balance connections even after repeated letters. 16 th and part bill submitted .

Chavara AE
Date: 26/06/2024

Work in progress | 85% Completed

18950m laying completed, 2195 connections completed, 16 th and part bill submitted.