Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

JJM-2021-22- WSS to Lakkidi Perur Panchayaths in Ottappalam Taluk – Phase – III

Project JJM-2021-22- WSS to Lakkidi Perur Panchayaths in Ottappalam Taluk – Phase – III
Project Code PKDJJM022212875
Type Main project
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description JJM-2021-22- WSS to Lakkidi Perur Panchayaths in Ottappalam Taluk – Phase – III
Status On-going
District Palakkad
Executing Office Shornur PH Dn
AS Amount (Rs) 289984000
AS Number G.O.(Rt)No.134/2022/WRD
TS Amount (Rs) 236200000
TS Number TS/5153/2022_5_1_1
Total Bill Submitted (Rs) 0
Total Bill Paid (Rs) 0
Population Benefitted 28000
Capacity in MLD 3.50
Actual Project Completion Date Date is not specified
Coverage WSS to Lakkidi Perur Panchayaths in Ottappalam Taluk

Packages

No. Project Name Location View
1 JJM-2021-22- WSS to Lakkidi Perur Panchayaths in Ottappalam Taluk – Phase – III Ottappalam PH Sn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
21 Feb 2024 PVC pipe laying in progress * Bill submitted to division. * 4 MLD Capacity Treatment Plant Design submitted to WASCON , approval to be obtained* Railway crossing permission obtained.* DI pipe line work started.150 mm DI - 690.0 m , 250 mm DI distribution pipe 690.65 m ,250 mm DI pumping main 689.6 m, 110 mm PVC 588.0 m,140 mm pvc 6kg -109.50 m Shornur PH Dn EE
22 Nov 2023 * PVC pipe laying in progress * Bill submitted to division. * 4 MLD Capacity Treatment Plant Design submitted to WASCON , approval to be obtained* Railway crossing permission obtained. Shornur PH Dn EE
13 Nov 2023 Joint inspection with PWD officials completed for PWD road cutting permission. Application submitted in Irrigation office for obtaining permission for laying pipe line along RBC canal Malampuzha . Pipe ordered by the contractor. Ottappalam PH Sn AE
08 Sep 2023 Joint inspection with PWD officials completed for PWD road cutting permission. Application submitted in Irrigation office for obtaining permission for laying pipe line along RBC canal Malampuzha . Pipe ordered by the contractor. Ottappalam PH Sn AE
20 Jul 2023 Joint inspection with PWD officials completed for PWD road cutting permission. Application submitted in Irrigation office for obtaining permission for laying pipe line along RBC canal Malampuzha . Pipe ordered by the contractor. Design drawing submitted to Division Shornur PH Dn EE

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 06/05/2023
Scheduled date of Completion of the Project 05 May 2024
Expected date of Completion 30/09/2024

Processing Dates

AS Date 23 Feb 2022
TS Date 08 Feb 2023

Other details

Project Officers View