JJM-2021-22- WSS to Lakkidi Perur Panchayaths in Ottappalam Taluk – Phase – III
Project |
JJM-2021-22- WSS to Lakkidi Perur Panchayaths in Ottappalam Taluk – Phase – III |
Project Code |
PKDJJM022212875 |
Type |
Main project |
Funding Agency |
JJM |
Category |
JJM |
Type of scheme |
Water Supply |
Scheme |
4215-01-102-92-02 |
Description |
JJM-2021-22- WSS to Lakkidi Perur Panchayaths in Ottappalam Taluk – Phase – III |
Status |
On-going |
District |
Palakkad |
Executing Office |
Shornur PH Dn |
AS Amount (Rs) |
289984000
|
AS Number |
G.O.(Rt)No.134/2022/WRD |
TS Amount (Rs) |
236200000 |
TS Number |
TS/5153/2022_5_1_1 |
Total Bill Submitted (Rs) |
0 |
Total Bill Paid (Rs) |
0 |
Population Benefitted |
28000 |
Capacity in MLD |
3.50 |
Actual Project Completion Date |
Date is not specified |
Coverage |
WSS to Lakkidi Perur Panchayaths in Ottappalam Taluk |
Packages
No. |
Project Name |
Location |
View |
1 |
JJM-2021-22- WSS to Lakkidi Perur Panchayaths in Ottappalam Taluk – Phase – III |
Ottappalam PH Sn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
21 Feb 2024 |
PVC pipe laying in progress * Bill submitted to division. * 4 MLD Capacity Treatment Plant Design submitted to WASCON , approval to be obtained* Railway crossing permission obtained.* DI pipe line work started.150 mm DI - 690.0 m , 250 mm DI distribution pipe 690.65 m ,250 mm DI pumping main 689.6 m, 110 mm PVC 588.0 m,140 mm pvc 6kg -109.50 m |
Shornur PH Dn EE |
|
22 Nov 2023 |
* PVC pipe laying in progress * Bill submitted to division. * 4 MLD Capacity Treatment Plant Design submitted to WASCON , approval to be obtained* Railway crossing permission obtained. |
Shornur PH Dn EE |
|
13 Nov 2023 |
Joint inspection with PWD officials completed for PWD road cutting permission. Application submitted in Irrigation office for obtaining permission for laying pipe line along RBC canal Malampuzha . Pipe ordered by the contractor. |
Ottappalam PH Sn AE |
|
08 Sep 2023 |
Joint inspection with PWD officials completed for PWD road cutting permission. Application submitted in Irrigation office for obtaining permission for laying pipe line along RBC canal Malampuzha . Pipe ordered by the contractor. |
Ottappalam PH Sn AE |
|
20 Jul 2023 |
Joint inspection with PWD officials completed for PWD road cutting permission. Application submitted in Irrigation office for obtaining permission for laying pipe line along RBC canal Malampuzha . Pipe ordered by the contractor. Design drawing submitted to Division |
Shornur PH Dn EE |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
06/05/2023 |
Scheduled date of Completion of the Project |
05 May 2024 |
Expected date of Completion |
30/09/2024 |
Processing Dates
AS Date |
23 Feb 2022 |
TS Date |
08 Feb 2023 |