Overall Project Status

Status Date Overall Project Status Project Officer Contact
28 Jun 2024 PVC pipe laying in progress * Bill submitted to division. * 4 MLD Capacity Treatment Plant Design submitted to WASCON , approval to be obtained* Railway crossing permission obtained.* DI pipe line work started.150 mm DI - 1700.0 m , 250 mm DI CWPM - 1330 m ,250 mm DI RWPM - 1800 m,250mm DI Distribution - 1030m, 110 mm PVC 588.0 m,140 mm pvc 6kg -406.00 m Ottappalam PH Sn AE
21 Feb 2024 PVC pipe laying in progress * Bill submitted to division. * 4 MLD Capacity Treatment Plant Design submitted to WASCON , approval to be obtained* Railway crossing permission obtained.* DI pipe line work started.150 mm DI - 690.0 m , 250 mm DI distribution pipe 690.65 m ,250 mm DI pumping main 689.6 m, 110 mm PVC 588.0 m,140 mm pvc 6kg -109.50 m Shornur PH Dn EE
22 Nov 2023 * PVC pipe laying in progress * Bill submitted to division. * 4 MLD Capacity Treatment Plant Design submitted to WASCON , approval to be obtained* Railway crossing permission obtained. Shornur PH Dn EE
13 Nov 2023 Joint inspection with PWD officials completed for PWD road cutting permission. Application submitted in Irrigation office for obtaining permission for laying pipe line along RBC canal Malampuzha . Pipe ordered by the contractor. Ottappalam PH Sn AE
08 Sep 2023 Joint inspection with PWD officials completed for PWD road cutting permission. Application submitted in Irrigation office for obtaining permission for laying pipe line along RBC canal Malampuzha . Pipe ordered by the contractor. Ottappalam PH Sn AE
20 Jul 2023 Joint inspection with PWD officials completed for PWD road cutting permission. Application submitted in Irrigation office for obtaining permission for laying pipe line along RBC canal Malampuzha . Pipe ordered by the contractor. Design drawing submitted to Division Shornur PH Dn EE
27 Jun 2023 Joint inspection with PWD officials completed for PWD road cutting permission. Application submitted in Irrigation office for obtaining permission for laying pipe line along RBC canal Malampuzha . Pipe ordered by the contractor. Ottappalam PH Sn AE
21 Jun 2023 Joint inspection with PWD officials completed for PWD road cutting permission. Application submitted in Irrigation office for obtaining permission for laying pipe line along RBC canal Malampuzha . Pipe ordered by the contractor. Ottappalam PH Sn AE
17 Jun 2023 Joint inspection with PWD officials completed for PWD road cutting permission. Application submitted in Irrigation office for obtaining permission for laying pipe line along RBC canal Malampuzha . Pipe ordered by the contractor. Ottappalam PH Sn AE
12 Jun 2023 Joint inspection with PWD officials completed for PWD road cutting permission. Application submitted in Irrigation office for obtaining permission for laying pipe line along RBC canal Malampuzha . Pipe ordered by the contractor. Ottappalam PH Sn AE