Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

JJM-2020-21-Thalayolaparambu Panchayath - Providing FHTC in various wards in Retrofitting the existing distribution system coming under jurisdiction of P H Division, Kaduthuruthy

Project JJM-2020-21-Thalayolaparambu Panchayath - Providing FHTC in various wards in Retrofitting the existing distribution system coming under jurisdiction of P H Division, Kaduthuruthy
Project Code KTMJJM08204328
Type Main project
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description JJM-2020-21-Thalayolaparambu Panchayath - Providing FHTC in various wards in Retrofitting the existing distribution system coming under jurisdiction of P H Division, Kaduthuruthy. Laying distribution lines 90mm PVC, 110 mm PVC, 80mm GI and 100mm GI - 18.82 Km and Providing FHTCs - 2358 Nos.
Status On-going
District Kottayam
Executing Office Kaduthuruthy PH Dn
AS Amount (Rs) 49151000
AS Number Go (Rt) No 541/2020/WRD dated 21/08/2020
TS Amount (Rs) 42780000
TS Number TS/2020-2021/2020/16502
Total Bill Submitted (Rs) 34589000
Total Bill Paid (Rs) 34589000
Population Benefitted 11790
Capacity in MLD 45.00
Actual Project Completion Date 28 Feb 2022
Coverage Population covered - 11790
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 Jal jeevan mission - (JJM)-2020-21-Phase I (Balance work) -Thalayolaparambu Panchayath - Providing FHTC and pipe laying works-pipe line wok . Vaikom Sn
2 JJM-2020-21-Thalayolaparambu Panchayath - Providing FHTC in various wards in Retrofitting the existing distribution system coming under jurisdiction of P H Division, Kaduthuruthy. Vaikom Sn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
30 Jun 2022 Work completed Kaduthuruthy Dn EE
29 Jun 2022 Work completed Kaduthuruthy Dn EE
28 Jun 2022 Work completed Kaduthuruthy Dn EE
27 Jun 2022 Work completed Kaduthuruthy Dn EE
26 Jun 2022 Work completed Kaduthuruthy Dn EE

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 27/11/2020
Scheduled date of Completion of the Project 04 May 2021
Expected date of Completion 17/03/2024

Processing Dates

AS Date 21 Aug 2020
TS Date 30 Aug 2020

Other details

Project Officers View