Jal jeevan mission - (JJM)-2020-21-Phase I (Balance work) -Thalayolaparambu Panchayath - Providing FHTC and pipe laying works-pipe line wok .

Project Jal jeevan mission - (JJM)-2020-21-Phase I (Balance work) -Thalayolaparambu Panchayath - Providing FHTC and pipe laying works-pipe line wok .
Project Code KTMJJM08204328P2
Type Package
Main Project JJM-2020-21-Thalayolaparambu Panchayath - Providing FHTC in various wards in Retrofitting the existing distribution system coming under jurisdiction of P H Division, Kaduthuruthy
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description Jal jeevan mission - (JJM)-2020-21-Phase I (Balance work) -Thalayolaparambu Panchayath - Providing FHTC and pipe laying works-pipe line wok .
Status On-going
District Kottayam
Executing Office Vaikom Sn
Agreement Number
Agreement Date
TS Amount (Rs) 5100000
TS Number WRD/KWA-CE(SR)/EST_TS/8145/2023_26_1_1
Technical specification Jal jeevan mission - (JJM)-2020-21-Phase I (Balance work) -Thalayolaparambu Panchayath - Providing FHTC and pipe laying works-pipe line wok .

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 18/09/2023
Scheduled date of Completion as per agreement 17 Mar 2024
Expected date of Completion 17/03/2024

Processing Dates

TS Date 29 Jul 2023
Estimate Approval 01 Sep 2023
NIT Approval 01 Sep 2023
Tender Closing 13 Sep 2023
Technichal Pre-Qualification 13 Sep 2023
Price bid opening 29 Jul 2023

Approval Dates

Workorder Date 13 Sep 2023
NA 18 Sep 2023

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Vaikom - AE
Date: 01/07/2024

Work in progress | 92% Completed

63 mm pvc =1115.50 mtr, 90 mm pvc= 149 mtr, 63 mm HDPE=178 mtr laid and total fhtc=70.

Vaikom - AE
Date: 30/06/2024

Work in progress | 92% Completed

63 mm pvc =1115.50 mtr, 90 mm pvc= 149 mtr, 63 mm HDPE=178 mtr laid and total fhtc=70.