Project | Budget -2017-2018-KIIFB project-TRAN10:WRD 025-13-WSS to Ramanchadi- Aligarh in Malappuram District Package 2 |
---|---|
Project Code | MLPKIIFB1118510P1 |
Type | Package |
Main Project | Budget -2017-2018-KIIFB project-TRAN10:WRD 025-13-WSS to Ramanchadi- Aligarh in Malappuram District |
Funding Agency | KIIFB |
Category | KIIFB |
Type of scheme | Water Supply |
Scheme | KIIFB |
Description | Supplying ,laying and testing distribution main - 350mm dia DI K9 -1230m 300mm dia.DI K9 -5270m 250mm dia,DI K9 -9333m 200mm dia,DI K9 -10962m 150mm dia,DI K9 -11900m 90mm PVC pipe -38695m Clear water gravity main DI K9 250mm - 8260m ratio labour: material - 4:9 for WSS to Ramanchadi Aligarh in Malappuram district -package2 |
Status | On-going |
District | Malappuram |
Executing Office | Malappuram Project Dn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 264000000 |
TS Number | TS/2019-2020/2019/11933 |
Technical specification | 350mm dia DI K9 -1230m 300mm dia.DI K9 -5270m 250mm dia,DI K9 -9333m 200mm dia,DI K9 -10962m 150mm dia,DI K9 -11900m 90mm PVC pipe -38695m Clear water gravity main DI K9 250mm - 8260m |
Contractor | Zubair V (Mob: 9447131582) |
Issue date | Solved On | Action Taken On | Category | Description | Comments | Issue Status |
---|---|---|---|---|---|---|
04 Oct 2021 | Pending | Pending | Road Cut Related Risk | Road cutting permission to be obtained from NHAI for replacement of old AC pipe with DI pipe(4.6 Km) in NH 966 | No comments available. | Pending |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 17/03/2020 |
---|---|
Scheduled date of Completion as per agreement | 28 Feb 2023 |
Expected date of Completion | 28/02/2023 |
TS Date | 11 Nov 2019 |
---|---|
Estimate Approval | 11 Nov 2019 |
NIT Approval | 21 Nov 2019 |
Tender Closing | 06 Mar 2020 |
Technichal Pre-Qualification | 29 Jan 2020 |
Price bid opening | 30 Jan 2020 |
Workorder Date | 13 Mar 2020 |
---|---|
NA | 03 Apr 2020 |
Malappuram Project Dn AE3 |
Date: 14/02/2024 |
Work in progress | 93% Completed
All works are completed except the replacement of old AC pipe with DI for a length of 4.5 KM along NH 966, as the road cutting permission was not obtained from the NHAI. So work short closed. .
Malappuram Project Dn AE3 |
Date: 13/02/2024 |
Work in progress | 93% Completed
All works are completed except the replacement of old AC pipe with DI for a length of 4.5 KM along NH 966, as the road cutting permission was not obtained from the NHAI. So work short closed. .