Budget -2017-2018-KIIFB project-TRAN10:WRD 025-13-WSS to Ramanchadi- Aligarh in Malappuram District Package 2

Project Budget -2017-2018-KIIFB project-TRAN10:WRD 025-13-WSS to Ramanchadi- Aligarh in Malappuram District Package 2
Project Code MLPKIIFB1118510P1
Type Package
Main Project Budget -2017-2018-KIIFB project-TRAN10:WRD 025-13-WSS to Ramanchadi- Aligarh in Malappuram District
Funding Agency KIIFB
Category KIIFB
Type of scheme Water Supply
Scheme KIIFB
Description Supplying ,laying and testing distribution main - 350mm dia DI K9 -1230m 300mm dia.DI K9 -5270m 250mm dia,DI K9 -9333m 200mm dia,DI K9 -10962m 150mm dia,DI K9 -11900m 90mm PVC pipe -38695m Clear water gravity main DI K9 250mm - 8260m ratio labour: material - 4:9 for WSS to Ramanchadi Aligarh in Malappuram district -package2
Status On-going
District Malappuram
Executing Office Malappuram Project Dn
Agreement Number
Agreement Date
TS Amount (Rs) 264000000
TS Number TS/2019-2020/2019/11933
Technical specification 350mm dia DI K9 -1230m 300mm dia.DI K9 -5270m 250mm dia,DI K9 -9333m 200mm dia,DI K9 -10962m 150mm dia,DI K9 -11900m 90mm PVC pipe -38695m Clear water gravity main DI K9 250mm - 8260m
Contractor Zubair V (Mob: 9447131582)

No project review have been added to this project

Reported Issues

Issue date Solved On Action Taken On Category Description Comments Issue Status
04 Oct 2021 Pending Pending Road Cut Related Risk Road cutting permission to be obtained from NHAI for replacement of old AC pipe with DI pipe(4.6 Km) in NH 966 No comments available. Pending

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 17/03/2020
Scheduled date of Completion as per agreement 28 Feb 2023
Expected date of Completion 28/02/2023

Processing Dates

TS Date 11 Nov 2019
Estimate Approval 11 Nov 2019
NIT Approval 21 Nov 2019
Tender Closing 06 Mar 2020
Technichal Pre-Qualification 29 Jan 2020
Price bid opening 30 Jan 2020

Approval Dates

Workorder Date 13 Mar 2020
NA 03 Apr 2020

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Malappuram Project Dn AE3
Date: 14/02/2024

Work in progress | 93% Completed

All works are completed except the replacement of old AC pipe with DI for a length of 4.5 KM along NH 966, as the road cutting permission was not obtained from the NHAI. So work short closed. .

Malappuram Project Dn AE3
Date: 13/02/2024

Work in progress | 93% Completed

All works are completed except the replacement of old AC pipe with DI for a length of 4.5 KM along NH 966, as the road cutting permission was not obtained from the NHAI. So work short closed. .