Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

KIIFB – 2017-18 Vandazhi, Kizhakkenchery, Vadakkanchery and Kannambra Panchayaths in Palakkad District – phase II - package I - Design, construction,Commissioning and Maintenance of 22.00 LL OHSR at Karimkunnam in Vadakkanchery Panchayath, Supplying and Laying 350mm DI K9 CWPM from WTP to Karimkunnam OHSR, Supplying and Erection of ,CW motor pump sets including road restoration work

Project KIIFB – 2017-18 Vandazhi, Kizhakkenchery, Vadakkanchery and Kannambra Panchayaths in Palakkad District – phase II - package I - Design, construction,Commissioning and Maintenance of 22.00 LL OHSR at Karimkunnam in Vadakkanchery Panchayath, Supplying and Laying 350mm DI K9 CWPM from WTP to Karimkunnam OHSR, Supplying and Erection of ,CW motor pump sets including road restoration work
Project Code PKDKIIFB1118631P1
Type Package
Main Project KIIFB -17-18 - Vandazhi, Kizhakkencherry, Vadakkencherry & Kannambra Comprehensive Fresh Water distribution project – Phase II in Palakkad District
Funding Agency KIIFB
Category KIIFB
Type of scheme Water Supply
Scheme KIIFB
Description Design, construction,commissioning and maintenance of 22 LL OHSR at Karimkunnam in Vadakkencherry grama Panchayat for feeding the Zone V and VI ie Low level zones of Vadakkencherry and Kannambra panchayaths and Supplying and laying of 350 mm DI K9 CWPM from the CW sump at WTP compound including road restoration work , Supply and erection of CW motor pumpset for pumping water to this OHSR. The permissive sanction obtained from the land owner for the construction of OHSR at Karimkunnam.
Status On-going
District Palakkad
Executing Office Chittur Project Dn
Agreement Number
Agreement Date
TS Amount (Rs) 150800000
TS Number 2019-2020/2019/15072 dated 13-12-2019
Technical specification Construction of 22 LL OHSR, Pipe line and pumpsets etc first time extension period to 12.09.2021
Contractor C.T Thambi (Mob: 9495321861)

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 13/03/2020
Scheduled date of Completion as per agreement 12 Mar 2021
Expected date of Completion 31/12/2023

Processing Dates

TS Date 13 Dec 2019
Estimate Approval 13 Dec 2019
NIT Approval 13 Dec 2019
Tender Closing 18 Jan 2020
Technichal Pre-Qualification 21 Jan 2020
Price bid opening 07 Feb 2020

Approval Dates

Workorder Date 13 Mar 2020
NA 23 Mar 2020

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Chittur Project Dn - AE 3
Date: 23/04/2024

Work in progress | 91% Completed

OHSR colour washing work and compound wall work are also in progress and, 350mm DI work- 15.00KM PIPE supplied at site and 14810.20km laid,GAP filling work is in progress.

Chittur Project Dn - AE 3
Date: 11/04/2024

Work in progress | 91% Completed

OHSR colour washing work and compound wall work are also in progress and, 350mm DI work- 15.00KM PIPE supplied at site and 14810.20km laid,GAP filling work is in progress.