KIIFB – 2017-18 Vandazhi, Kizhakkenchery, Vadakkanchery and Kannambra Panchayaths in Palakkad District – phase II - package I - Design, construction,Commissioning and Maintenance of 22.00 LL OHSR at Karimkunnam in Vadakkanchery Panchayath, Supplying and Laying 350mm DI K9 CWPM from WTP to Karimkunnam OHSR, Supplying and Erection of ,CW motor pump sets including road restoration work
Project |
KIIFB – 2017-18 Vandazhi, Kizhakkenchery, Vadakkanchery and Kannambra Panchayaths in Palakkad District – phase II - package I - Design, construction,Commissioning and Maintenance of 22.00 LL OHSR at Karimkunnam in Vadakkanchery Panchayath, Supplying and Laying 350mm DI K9 CWPM from WTP to Karimkunnam OHSR, Supplying and Erection of ,CW motor pump sets including road restoration work |
Project Code |
PKDKIIFB1118631P1 |
Type |
Package |
Main Project |
KIIFB -17-18 - Vandazhi, Kizhakkencherry, Vadakkencherry & Kannambra Comprehensive Fresh Water distribution project – Phase II in Palakkad District
|
Funding Agency |
KIIFB |
Category |
KIIFB |
Type of scheme |
Water Supply |
Scheme |
KIIFB |
Description |
Design, construction,commissioning and maintenance of 22 LL OHSR at Karimkunnam in Vadakkencherry grama Panchayat for feeding the Zone V and VI ie Low level zones of Vadakkencherry and Kannambra panchayaths and Supplying and laying of 350 mm DI K9 CWPM from the CW sump at WTP compound including road restoration work , Supply and erection of CW motor pumpset for pumping water to this OHSR. The permissive sanction obtained from the land owner for the construction of OHSR at Karimkunnam. |
Status |
On-going |
District |
Palakkad |
Executing Office |
Chittur Project Dn |
Agreement Number |
|
Agreement Date |
|
TS Amount (Rs) |
150800000 |
TS Number |
2019-2020/2019/15072 dated 13-12-2019 |
Technical specification |
Construction of 22 LL OHSR, Pipe line and pumpsets etc
first time extension period to 12.09.2021 |
Contractor |
C.T Thambi (Mob: 9495321861) |
No project review have been added to this project
Project Progress Status
|
Project Progress Status
|
Duration & Sanction dates
Date of start of Package |
13/03/2020 |
Scheduled date of Completion as per agreement |
12 Mar 2021 |
Expected date of Completion |
31/12/2023 |
Processing Dates
TS Date |
13 Dec 2019 |
Estimate Approval |
13 Dec 2019 |
NIT Approval |
13 Dec 2019 |
Tender Closing |
18 Jan 2020 |
Technichal Pre-Qualification |
21 Jan 2020 |
Price bid opening |
07 Feb 2020 |
Approval Dates
Workorder Date |
13 Mar 2020 |
NA |
23 Mar 2020 |
Other details
Project Schedule |
View |
Project Components |
View |
Project Officers |
View |
Chittur Project Dn - AE 3 |
Date: 23/04/2024 |
Work in progress | 91% Completed
OHSR colour washing work and compound wall work are also in progress and, 350mm DI work- 15.00KM PIPE supplied at site and 14810.20km laid,GAP filling work is in progress.
Chittur Project Dn - AE 3 |
Date: 11/04/2024 |
Work in progress | 91% Completed
OHSR colour washing work and compound wall work are also in progress and, 350mm DI work- 15.00KM PIPE supplied at site and 14810.20km laid,GAP filling work is in progress.