Project | AMRUT-AMRUT 2.0 - SWAP-2- PIPE LINE EXTENSION , PROVIDING WATER CONNECTIONS IN VARIOUS ZONES OF KANNUR CORPORATION -KANNUR MUNICIPAL AREA(OLD) UNDER WS SECTION III KANNUR - Pipeline work |
---|---|
Project Code | KNRAMRUT 2032314178P1 |
Type | Package |
Main Project | AMRUT-AMRUT 2.0 - SWAP-2- PIPE LINE EXTENSION , PROVIDING WATER CONNECTIONS IN VARIOUS ZONES OF KANNUR CORPORATION -KANNUR MUNICIPAL AREA(OLD) UNDER WS SECTION III KANNUR - Pipeline work |
Funding Agency | AMRUT 2 |
Category | AMRUT 2 |
Type of scheme | Water Supply |
Scheme | |
Description | AMRUT-AMRUT 2.0 - SWAP-2- PIPE LINE EXTENSION , PROVIDING WATER CONNECTIONS IN VARIOUS ZONES OF KANNUR CORPORATION -KANNUR MUNICIPAL AREA(OLD) UNDER WS SECTION III KANNUR - Pipeline work |
Status | On-going |
District | Kannur |
Executing Office | Kannur WS Sn 3 |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 88900000 |
TS Number | WRD/KWA-CE(NR)/EST-TS/674/2022-26-3-2 |
Technical specification |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | Date is not specified |
---|---|
Scheduled date of Completion as per agreement | Date is not specified |
Expected date of Completion | Date is not specified |
TS Date | 08 May 2023 |
---|
Kannur PH Sn 3 AE |
Date: 27/06/2024 |
Work in progress | 55% Completed
7.5 KM Pipe laid 595 connections given..
Kannur PH Sn 3 AE |
Date: 24/06/2024 |
Work in progress | 55% Completed
7.5 KM Pipe laid 595 connections given..