AMRUT-AMRUT 2.0 - SWAP-2- PIPE LINE EXTENSION , PROVIDING WATER CONNECTIONS IN VARIOUS ZONES OF KANNUR CORPORATION -KANNUR MUNICIPAL AREA(OLD) UNDER WS SECTION III KANNUR - Pipeline work

Project AMRUT-AMRUT 2.0 - SWAP-2- PIPE LINE EXTENSION , PROVIDING WATER CONNECTIONS IN VARIOUS ZONES OF KANNUR CORPORATION -KANNUR MUNICIPAL AREA(OLD) UNDER WS SECTION III KANNUR - Pipeline work
Project Code KNRAMRUT 2032314178
Type Main project
Funding Agency AMRUT 2
Category AMRUT 2
Type of scheme Water Supply
Scheme
Description AMRUT-AMRUT 2.0 - SWAP-2- PIPE LINE EXTENSION , PROVIDING WATER CONNECTIONS IN VARIOUS ZONES OF KANNUR CORPORATION -KANNUR MUNICIPAL AREA(OLD) UNDER WS SECTION III KANNUR - Pipeline work
Status On-going
District Kannur
Executing Office Kannur WS Dn
AS Amount (Rs) 699900000
AS Number G.O (Rt)No.677/2023/LSGD
TS Amount (Rs) 88900000
TS Number WRD/KWA-CE(NR)/EST-TS/674/2022-26-3-2
Total Bill Submitted (Rs)
Total Bill Paid (Rs)
Population Benefitted
Capacity in MLD
Actual Project Completion Date Date is not specified
Coverage

Packages

No. Project Name Location View
1 AMRUT-AMRUT 2.0 - SWAP-2- PIPE LINE EXTENSION , PROVIDING WATER CONNECTIONS IN VARIOUS ZONES OF KANNUR CORPORATION -KANNUR MUNICIPAL AREA(OLD) UNDER WS SECTION III KANNUR - Pipeline work Kannur WS Sn 3

Overall Project Status

Status Date Overall Project Status Project Officer Contact
01 Jun 2024 7.5 KM Pipe laid 595 connections given. Kannur PH Sn 3 AE
18 May 2024 7 KM Pipe laid 590 connections given Kannur PH Sn 3 AE
02 May 2024 6.4 km pipe laid 580 Connections given Kannur PH Sn 3 AE
18 Apr 2024 40% Completed, Pipe laid- 6km, FHTC-555 Kannur PH Sn 3 AE
12 Apr 2024 WORK IN PROGRESS Kannur PH Sn 3 AE

No project review have been added to this project

Duration & Sanction dates

Date of start of Project Date is not specified
Scheduled date of Completion of the Project Date is not specified
Expected date of Completion Date is not specified

Processing Dates

AS Date 21 Mar 2023
TS Date 08 May 2023

Other details