Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

PACKAGE I-Design & construction of 6m dia. Intake well cum pump house.Supplying, laying, Commissioning and maintaining 400mm DI K9 RWPM from Intake well to WTP.Supply, Erection and Commissioning of 3 Nos. of 110HP VT Raw Water Pump sets, Electrical substation,erection of 400KVA USS indoor transformer and allied works.

Project PACKAGE I-Design & construction of 6m dia. Intake well cum pump house.Supplying, laying, Commissioning and maintaining 400mm DI K9 RWPM from Intake well to WTP.Supply, Erection and Commissioning of 3 Nos. of 110HP VT Raw Water Pump sets, Electrical substation,erection of 400KVA USS indoor transformer and allied works.
Project Code KLMGOK0117468P1
Type Package
Main Project PROJECTS UNDER KERALA INFRA.INVT. FUND BOARD KIIFB(74)--WSS to Kalluvathukkal Parippallay and Velinalloor(Part) Villages-Phase I (7520)
Funding Agency KIIFB
Category KIIFB
Type of scheme Water Supply
Scheme KIIFB
Description PACKAGE I-Design & construction of 6m dia. Intake well cum pump house.Supplying, laying, Commissioning and maintaining 400mm DI K9 RWPM from Intake well to WTP.Supply, Erection and Commissioning of 3 Nos. of 110HP VT Raw Water Pump sets, Electrical substation,erection of 400KVA USS indoor transformer and allied works.
Status On-going
District Kollam
Executing Office Kollam Project Dn
Agreement Number
Agreement Date
TS Amount (Rs) 58210000
TS Number 9161/2019
Technical specification CONSTRUCTION OF 6M DIA WELL,400 mm DI K9 RWPM,110 HP VT RWPS,400KVa TRANSFORMER ROOM AND ERECTION OF TRANSFORMER.
Contractor Sivaprasad S (Mob: 9447206962)

Project Review

See All Review messages
Review Date Review Message Review Attended By
18 Dec 2021 UP DATE THE STATUS AE

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 07/02/2020
Scheduled date of Completion as per agreement 05 Apr 2022
Expected date of Completion 31/08/2022

Processing Dates

TS Date 24 Mar 2017
Estimate Approval 22 Aug 2019
NIT Approval 22 Aug 2019
Tender Closing 17 Oct 2019
Technichal Pre-Qualification 11 Dec 2019
Price bid opening 23 Dec 2019

Approval Dates

Workorder Date 21 Jan 2020
NA 07 Feb 2020

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Kollam Project HD
Date: 15/06/2023

Work has been completed | 100% Completed

Trial run and commissioning completed.

Kollam Project HD
Date: 12/03/2023

Work has been completed | 100% Completed

Trial run carried out, awaiting commissioning..