PROJECTS UNDER KERALA INFRA.INVT. FUND BOARD KIIFB(74)--WSS to Kalluvathukkal Parippallay and Velinalloor(Part) Villages-Phase I (7520)

Project PROJECTS UNDER KERALA INFRA.INVT. FUND BOARD KIIFB(74)--WSS to Kalluvathukkal Parippallay and Velinalloor(Part) Villages-Phase I (7520)
Project Code KLMKIIFB0117468
Type Main project
Funding Agency KIIFB
Category KIIFB
Type of scheme Water Supply
Scheme KIIFB
Description KIIFB-WSS to Kalluvathukkal Parippallay and Velinalloor(Part) Villages-Phase I
Status On-going
District Kollam
Executing Office Kollam Project Dn
AS Amount (Rs) 270000000
AS Number 14/2017
TS Amount (Rs) 270000000
TS Number 26/2016-17
Total Bill Submitted (Rs) 187974281
Total Bill Paid (Rs) 187974281
Population Benefitted 42929
Capacity in MLD 7.50
Actual Project Completion Date 12 Mar 2022
Coverage 68347
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 PACKAGE I-Design & construction of 6m dia. Intake well cum pump house.Supplying, laying, Commissioning and maintaining 400mm DI K9 RWPM from Intake well to WTP.Supply, Erection and Commissioning of 3 Nos. of 110HP VT Raw Water Pump sets, Electrical substation,erection of 400KVA USS indoor transformer and allied works. Kollam Project Dn
2 "PACKAGE II-Design, Construction and commissioning of 7.5 MLD conventional type rapid sand filter Water Treatment Plant (WTP) including 4.50 LL CW sump Construction of 9.0 Lakhs Litrecapacity OHSR at Kattupuram, Supply, Erection and Commissioning of Clear Water Pump sets , Supplying Laying and commissioning of 350mm DI K9 Clear Water Pumping Main" Kollam Project Dn
3 PACKAGE III-Construction of new weir at Mannayam, about three KMs upstream side of the Aduthala bridge. Kollam Project Dn
4 PACKAGE IV-Rehabilitation of existing 1.5 MLD (slow sand filter)Treatment plant at Velinalloor Kollam Project Dn
5 PACKAGE VI- Providing scour line from WTP to mannayam bridge, Providing RR masonry at well site as protection works , providing interlock in approach road and construction of washroom at well site for operators. -General Civil Work Kollam Project Dn
6 PACKAGE V-Strengthening of the existing weir constructed by the Irrigation department at Aduthala and its allied works Kollam Project Dn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
14 Nov 2023 Out of 6 packages, 3 nos completed.. Packages 3 for construction of weir is in progress. Packages 5 for reformation of weir is temporarily stopped due to high water table. Packages 6 for Constrution of retaining wall and laying of scour line from WTP are in progress. Kollam Project HD
15 Jun 2023 One new package were added. Out of 6 packages, 3 nos completed.. Packages 3 for construction of weir is in progress. Packages 5 for reformation of weir is temporarily stopped due to high water table. Packages 6 for Constrution of retaining wall and laying of scour line from WTP are in progress. Kollam Project HD
03 Apr 2023 Out of 5 packages, 2 nos completed. Package 2 99% completed except NHAI crossing at Kalluvathukkal Jn which is scheduled to start on 05.04.2023. Packages 3 & 5 for construction and reformation of weirs are in progress. Kollam Project Dn EE
11 Jun 2022 NHAI deputy manager (Technical )visited Kalluvathukkal crossing point with KWA officials and NHAI Contractors representatives for ensuring Technical feasibility of crossing on 10.06.2022 Kollam Project HD
26 May 2022 NHAI representative assured to accord sanction for NH 66 crossing at Kalluvathukkal junction within one week in Road coordination committee held in the chamber of Hon District Collector Kollam on 26-05-22 Kollam Project HD

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 04/03/2018
Scheduled date of Completion of the Project 12 Mar 2022
Expected date of Completion 30/09/2023

Processing Dates

AS Date 11 Jan 2017
TS Date 24 Mar 2017