Project | NRDWP-WSSto vakathanam pt: 12m dia well com p/H at peroor |
---|---|
Project Code | KTMGOI11124368P1 |
Type | Package |
Main Project | NRDWP_ ARWSS to VAkathanam Panchayat |
Funding Agency | GOI |
Category | ARWSS (50% State share) |
Type of scheme | Water Supply |
Scheme | |
Description | 12m dia well cum pumphouse and allied works at peroor |
Status | On-going |
District | Kottayam |
Executing Office | Kottayam Project Dn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 38500000 |
TS Number | TS No |
Technical specification | 12m dia well and pumphouse |
Contractor | PAULOSE ABRAHAM (Mob: 9447378939) |
Issue date | Solved On | Action Taken On | Category | Description | Comments | Issue Status |
---|---|---|---|---|---|---|
11 Oct 2021 | 30 Nov 2021 | Pending | Natural Calamities Related | flooding in river | Issues related to flooding resolved by end of November 30.11.21 | Solved |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 26/02/2014 |
---|---|
Scheduled date of Completion as per agreement | 30 Dec 2014 |
Expected date of Completion | 30/06/2022 |
TS Date | 29 Nov 2012 |
---|---|
Estimate Approval | 07 Jun 2012 |
NIT Approval | 13 Mar 2013 |
Tender Closing | 20 Mar 2013 |
Technichal Pre-Qualification | 02 Apr 2013 |
Price bid opening | 20 May 2021 |
Workorder Date | 12 Jun 2013 |
---|---|
NA | 25 Jun 2013 |
Kottayam AE 3 |
Date: 28/03/2022 |
Work has been completed | 100% Completed
Work is substantially completed..
Kottayam AE 3 |
Date: 26/03/2022 |
Work in progress | 99% Completed
Work is substantially completed..