Project | NRDWP_ ARWSS to VAkathanam Panchayat |
---|---|
Project Code | KTMGOI11124368 |
Type | Main project |
Funding Agency | GOI |
Category | ARWSS (50% State share) |
Type of scheme | Water Supply |
Scheme | |
Description | 12m dia well cum pump house,leading pipe works,10 ton gantry crane,landscaping works. |
Status | On-going |
District | Kottayam |
Executing Office | Kottayam Project Dn |
AS Amount (Rs) | 300000000 |
AS Number | WS/65/2012-13 |
TS Amount (Rs) | 38500000 |
TS Number | KWA/CE(SR)/PHTVL/3478/2011 |
Total Bill Submitted (Rs) | 21810633 |
Total Bill Paid (Rs) | 21810633 |
Population Benefitted | 125000 |
Capacity in MLD | 62.50 |
Actual Project Completion Date | 31 Dec 2021 |
Coverage | 12m dia well cum Pumphouse- Common component of 4 schemes such as Augmentation of UWSS to Kottayam Municipality, WSS to PUthguppally and Meenadom, WSS to Vakathanam, WSS to Vijayapuram. |
Implementation Schedule | Download |
Work Plan | Download |
Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
08 Mar 2022 | Leading pipe laying two number of options completed. Construction of chamber at the end of leading pipe is in progress. | Kottayam AE 3 | |
27 Dec 2021 | 10 ton crane erected. Compound wall works and gate fabrication works are ongoing.Yard development works are progressing | Kottayam AE 3 | |
21 Dec 2021 | **90% physical progress. **64% financial progress. Hindrance due to heavy rain occurred in the month of November delayed the leading pipe laying works.At present the following are the status of individual components: Well cum pumphouse-completed compound wall-in progress Retaining wall-completed Gate fixing works-started road tarring-materials procurement in progress leading pipe works-not started. | Kottayam AE 3 | |
16 Dec 2021 | Agreement for EOT executed till 31.12.2021 as per Hon'ble high court judgement. EOT crane 10 T erection works in progress. Compound wall works in progress. Leading pipe installation is pending due to high water level at Meenachal river and planned start on 20th Decemeber. Road work in those stretches where further trenching is not planned in forthcoming works is identifies and instructed to start ASAP. | Meenachal-Malankara Project Dn AEE1 | |
05 Nov 2021 | Contractor informed that Hon. High Court has granted extension for time of completion for the work until 31.12.2021. Directed him to produce the judgement regarding the same. | Kottayam Project Dn EE |
Review Date | Review Message | Review Attended By |
---|---|---|
21 Dec 2021 | Online review meeting conducted by MD,KWA on 21.12.21 for the work and attended. DCE directed to complete the work at the earliest. | EE |
11 Oct 2021 | Please update the latest status of work with Schedule of completion |
Date of start of Project | 26/02/2014 |
---|---|
Scheduled date of Completion of the Project | 24 Dec 2014 |
Expected date of Completion | 30/06/2022 |
AS Date | 06 Nov 2012 |
---|---|
TS Date | 29 Nov 2012 |
Project Officers | View |
---|