Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

NRDWP_ ARWSS to VAkathanam Panchayat

Project NRDWP_ ARWSS to VAkathanam Panchayat
Project Code KTMGOI11124368
Type Main project
Funding Agency GOI
Category ARWSS (50% State share)
Type of scheme Water Supply
Scheme
Description 12m dia well cum pump house,leading pipe works,10 ton gantry crane,landscaping works.
Status On-going
District Kottayam
Executing Office Kottayam Project Dn
AS Amount (Rs) 300000000
AS Number WS/65/2012-13
TS Amount (Rs) 38500000
TS Number KWA/CE(SR)/PHTVL/3478/2011
Total Bill Submitted (Rs) 21810633
Total Bill Paid (Rs) 21810633
Population Benefitted 125000
Capacity in MLD 62.50
Actual Project Completion Date 31 Dec 2021
Coverage 12m dia well cum Pumphouse- Common component of 4 schemes such as Augmentation of UWSS to Kottayam Municipality, WSS to PUthguppally and Meenadom, WSS to Vakathanam, WSS to Vijayapuram.
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 NRDWP-WSSto vakathanam pt: 12m dia well com p/H at peroor Kottayam Project Dn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
08 Mar 2022 Leading pipe laying two number of options completed. Construction of chamber at the end of leading pipe is in progress. Kottayam AE 3
27 Dec 2021 10 ton crane erected. Compound wall works and gate fabrication works are ongoing.Yard development works are progressing Kottayam AE 3
21 Dec 2021 **90% physical progress. **64% financial progress. Hindrance due to heavy rain occurred in the month of November delayed the leading pipe laying works.At present the following are the status of individual components: Well cum pumphouse-completed compound wall-in progress Retaining wall-completed Gate fixing works-started road tarring-materials procurement in progress leading pipe works-not started. Kottayam AE 3
16 Dec 2021 Agreement for EOT executed till 31.12.2021 as per Hon'ble high court judgement. EOT crane 10 T erection works in progress. Compound wall works in progress. Leading pipe installation is pending due to high water level at Meenachal river and planned start on 20th Decemeber. Road work in those stretches where further trenching is not planned in forthcoming works is identifies and instructed to start ASAP. Meenachal-Malankara Project Dn AEE1
05 Nov 2021 Contractor informed that Hon. High Court has granted extension for time of completion for the work until 31.12.2021. Directed him to produce the judgement regarding the same. Kottayam Project Dn EE

Project Review

See All Review messages
Review Date Review Message Review Attended By
21 Dec 2021 Online review meeting conducted by MD,KWA on 21.12.21 for the work and attended. DCE directed to complete the work at the earliest. EE
11 Oct 2021 Please update the latest status of work with Schedule of completion

Duration & Sanction dates

Date of start of Project 26/02/2014
Scheduled date of Completion of the Project 24 Dec 2014
Expected date of Completion 30/06/2022

Processing Dates

AS Date 06 Nov 2012
TS Date 29 Nov 2012

Other details

Project Officers View