Project | Package II- Supply and laying Distribution network and Providing FHTC to house holds of Kudayathoor Panchayath |
---|---|
Project Code | IDKJJM022211097P1 |
Type | Package |
Main Project | JJM - Providing FHTC to house holds of Kudayathoor Panchayath |
Funding Agency | JJM |
Category | JJM |
Type of scheme | Water Supply |
Scheme | 4215-01-102-92-02 |
Description | The project includes Pumping mains, Distribution, sump cum pump house, GLSRs, Pumpsets and Providing FHTC |
Status | On-going |
District | Idukki |
Executing Office | Kattappana Project Dn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 217000000 |
TS Number | WRD/KWA-CEP/EST_TS/368/2022_5_2_1 |
Technical specification |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 01/03/2023 |
---|---|
Scheduled date of Completion as per agreement | Date is not specified |
Expected date of Completion | Date is not specified |
TS Date | 13 Sep 2022 |
---|---|
Estimate Approval | 13 Sep 2022 |
NIT Approval | 09 Nov 2022 |
Tender Closing | 07 Nov 2022 |
Technichal Pre-Qualification | 14 Dec 2022 |
Price bid opening | 16 Dec 2022 |
Workorder Date | 24 Feb 2023 |
---|
Kattapana Project Dn AE4 |
Date: 15/06/2024 |
Work in progress | 55% Completed
Wall shuttering sump cum pump house morkad.
Kattapana Project Dn AE4 |
Date: 11/06/2024 |
Work in progress | 54% Completed
Deshuttering work at morkkad sump cum pump house.