Project | JJM-VLLIYAMATTOM |
---|---|
Project Code | IDKJJM08203385 |
Type | Main project |
Funding Agency | JJM |
Category | JJM |
Type of scheme | Water Supply |
Scheme | 4215-01-102-92-02 |
Description | JJM-VELLIYAMATTOM- PROVIDING FHTC TO HOUSEHOLDS OF VELLIYAMATTOM PANCHAYATH IN IDUKKI DISTRICT |
Status | Completed |
District | Idukki |
Executing Office | Kattappana Project Dn |
AS Amount (Rs) | 29860000 |
AS Number | GO(Rt)541/2020/WRD dtd 21/08/2020 |
TS Amount (Rs) | 9899000 |
TS Number | TS/2020-2021/2020/19451 Dated: 26-08-2020 |
Total Bill Submitted (Rs) | 30025384 |
Total Bill Paid (Rs) | 30025384 |
Population Benefitted | 18850 |
Capacity in MLD | 4.00 |
Actual Project Completion Date | Date is not specified |
Coverage | VELLIYAMATTOM PANCHAYATH |
Implementation Schedule | Download |
Work Plan | Download |
Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
08 Feb 2022 | The whole project completed. | Kattapana Project Dn AE4 | |
08 Feb 2022 | Package 1 completed. Package 2- 99% completed, | Kattappana Project Dn EE | |
15 Nov 2021 | Power connection works in progress | Kattapana Project Dn AE4 | |
10 Sep 2021 | Estimate under scrutiny for Technical Sanction. | Kattapana Project Dn AE4 | |
10 Sep 2021 | Providing FHTC - Completed. The installation of pumpset is under progress. Power connection to be received from KSEB | Kattapana Project Dn AE4 |
Date of start of Project | 17/09/2020 |
---|---|
Scheduled date of Completion of the Project | 30 Apr 2021 |
Expected date of Completion | 10/10/2021 |
AS Date | 21 Aug 2020 |
---|---|
TS Date | 28 Aug 2020 |
Project Officers | View |
---|