Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
08 Feb 2022 | The whole project completed. | Kattapana Project Dn AE4 | |
08 Feb 2022 | Package 1 completed. Package 2- 99% completed, | Kattappana Project Dn EE | |
15 Nov 2021 | Power connection works in progress | Kattapana Project Dn AE4 | |
10 Sep 2021 | Estimate under scrutiny for Technical Sanction. | Kattapana Project Dn AE4 | |
10 Sep 2021 | Providing FHTC - Completed. The installation of pumpset is under progress. Power connection to be received from KSEB | Kattapana Project Dn AE4 | |
07 Sep 2021 | Providing FHTC-2200 nos- completed. Supply and Erection of Pumpset is under progress. | Kattapana Project Dn AE4 | |
19 Mar 2021 | Pipe laying work in progress ,1776 FHTCs given | Kattappana Project Dn EE | |
15 Mar 2021 | Total 1401 FHTCs out of 2200 FHTCs are billed | Kattapana Project Dn AE4 | |
30 Jan 2021 | CC 2nd and Part Bill for 552nos FHTCs under scrutiny in Division Office | Kattappana Project Dn EE | |
26 Jan 2021 | Work is in Progress. Second Part Bill for 550 FHTCs are submitted | Kattapana Project Dn AE4 |