Overall Project Status

Status Date Overall Project Status Project Officer Contact
08 Feb 2022 The whole project completed. Kattapana Project Dn AE4
08 Feb 2022 Package 1 completed. Package 2- 99% completed, Kattappana Project Dn EE
15 Nov 2021 Power connection works in progress Kattapana Project Dn AE4
10 Sep 2021 Estimate under scrutiny for Technical Sanction. Kattapana Project Dn AE4
10 Sep 2021 Providing FHTC - Completed. The installation of pumpset is under progress. Power connection to be received from KSEB Kattapana Project Dn AE4
07 Sep 2021 Providing FHTC-2200 nos- completed. Supply and Erection of Pumpset is under progress. Kattapana Project Dn AE4
19 Mar 2021 Pipe laying work in progress ,1776 FHTCs given Kattappana Project Dn EE
15 Mar 2021 Total 1401 FHTCs out of 2200 FHTCs are billed Kattapana Project Dn AE4
30 Jan 2021 CC 2nd and Part Bill for 552nos FHTCs under scrutiny in Division Office Kattappana Project Dn EE
26 Jan 2021 Work is in Progress. Second Part Bill for 550 FHTCs are submitted Kattapana Project Dn AE4