Jal Jeevan Mission- 2021-22- Providing functional house hold Tap connections in Elamkulam Grama Panchayath-Phase-2

Project Jal Jeevan Mission- 2021-22- Providing functional house hold Tap connections in Elamkulam Grama Panchayath-Phase-2
Project Code MLPJJM09219076P1
Type Package
Main Project Jal Jeevan Mission - 2021-22 - Providing functional house hold Tap connections in Elamkulam Grama Panchayath-Phase-2
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description Construction of OHSR 8LL, VALVE CHAMBER, FHTCs -2000nos, tank -inter connection works, compound wall, OH Tank 2.25ll pump set, design and survey of new distribution lines
Status On-going
District Malappuram
Executing Office Perinthalmanna PH Sn
Agreement Number
Agreement Date
TS Amount (Rs) 151100000
TS Number Reg .No. 15525/2021-2022
Technical specification Construction of OHSR 8LL, VALVE CHAMBER, FHTCs -2000nos, tank -inter connection works, compound wall, OH Tank 2.25ll pump set, design and survey of new distribution lines

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 05/04/2022
Scheduled date of Completion as per agreement 21 Jan 2023
Expected date of Completion 21/01/2023

Processing Dates

TS Date 16 Dec 2021
Estimate Approval 16 Dec 2021
NIT Approval 16 Dec 2021
Tender Closing 24 Feb 2022
Technichal Pre-Qualification 18 Feb 2022
Price bid opening 18 Feb 2022

Approval Dates

Workorder Date 22 Mar 2022
NA 05 Apr 2022

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Perinthalmanna AE
Date: 28/06/2024

Work in progress | 90% Completed

both 8LL Perumbaramb OHSR & 2.25 LL Parakkunnu OHSR concrete completed. Both tanks plastering and painting work completed. Both tanks stainless steel handrail work completed. 250mm DI 1600m laid, 160mm PE 2700.5m laid, 90mm PE 18500.5m laid, 110mm PE 1500m laid, 140mm PE 1300m laid. 1892 FHTC and 418HTC given.construction of valve chamber completed. .

Perinthalmanna AE
Date: 24/06/2024

Work in progress | 90% Completed

both 8LL Perumbaramb OHSR & 2.25 LL Parakkunnu OHSR concrete completed. Both tanks plastering and painting work completed. Both tanks stainless steel handrail work completed. 250mm DI 1600m laid, 160mm PE 2700.5m laid, 90mm PE 18500.5m laid, 110mm PE 1500m laid, 140mm PE 1300m laid. 1892 FHTC and 418HTC given.construction of valve chamber completed. .