Project | KIIFB-PROJECT TRANCHE-8-WRD- 025-14-COMPREHENSIVE DRINKING WATER SUPPLY SCHEME TO EDAVANNA PANCHAYATH IN MALAPPURAM DISTRICT - PACKAGE-I |
---|---|
Project Code | MLPKIIFB0218679P1 |
Type | Package |
Main Project | KIIFB – PROJECT TRANCHE-8-WRD025 - 14 WSS to Edavanna Panchayath in Malappuram District |
Funding Agency | KIIFB |
Category | KIIFB |
Type of scheme | Water Supply |
Scheme | KIIFB |
Description | COMPREHENSIVE DRINKING WATER SUPPLY SCHEME TO EDAVANNA PANCHAYATH IN MALAPPURAM DISTRICT - PACKAGE-I-400mm DI K9 RWPM-1950m, 9 MLD Plant with SCADA, 4.0LL CW Sump,18.20LL GLSR&11.90 LLOHSR, 300mm DI K9 CW Pumping Main -50m, 300MM DI K7 -Wash Water Disposal line-1050m, Approach road, retaining Walls,216 HP RW pumpsets,20HP Cf CW pumpsets &Clear water pump house etc |
Status | On-going |
District | Malappuram |
Executing Office | Malappuram Project Dn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 160800000 |
TS Number | 6640/2019-20 |
Technical specification | PACKAGE-I-400mm DI K9 RWPM-1750m, 9 MLD Plant with SCADA, 4.0LL CW Sump,18.20LL GLSR&11.90 LLOHSR, 300mm DI K9 CW Pumping Main -50m, 300MM DI K7 -Wash Water Disposal line-800m, Approach road, retaining Walls,216 HP RW pumpsets,20HP Cf CW pumpsets Clear water pump house etc |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 18/03/2020 |
---|---|
Scheduled date of Completion as per agreement | 05 Jun 2021 |
Expected date of Completion | 31/05/2023 |
TS Date | 12 Dec 2019 |
---|---|
Estimate Approval | 12 Dec 2019 |
NIT Approval | 21 Dec 2019 |
Tender Closing | 13 Jan 2020 |
Technichal Pre-Qualification | 22 Jan 2020 |
Price bid opening | 30 Jan 2020 |
Workorder Date | 07 Mar 2020 |
---|---|
NA | 16 Mar 2020 |
Malappuram Project Dn |
Date: 01/04/2024 |
Work in progress | 92% Completed
Scheme commission on 19-5-2023 - charging of distribution line progressing .
Malappuram Project Dn |
Date: 31/03/2024 |
Work in progress | 92% Completed
Scheme commission on 19-5-2023 - charging of distribution line progressing .