| Project | AMRUT-1.0 - KOZHIKODE WATER SUPPLY PROJECT-REPLACING OLD DAMAGED PIPES AND LAYING NEW PIPE LINES IN BEYPORE ZONE -Pipeline Work |
|---|---|
| Project Code | CLTAMRUT032313801P33 |
| Type | Package |
| Main Project | AMRUT 1.0-Kozhikode Water Supply Project-Providing FHTCs and Pipe Line extension |
| Funding Agency | AMRUT |
| Category | AMRUT |
| Type of scheme | Water Supply |
| Scheme | AMRUT |
| Description | AMRUT-1.0 - KOZHIKODE WATER SUPPLY PROJECT-REPLACING OLD DAMAGED PIPES AND LAYING NEW PIPE LINES IN BEYPORE ZONE -Pipeline Work |
| Status | On-going |
| District | Kozhikkode |
| Executing Office | Kozhikode Dist 1 Sn 3 |
| Agreement Number | |
| Agreement Date | |
| TS Amount (Rs) | 33000000 |
| TS Number | 17436/2022-2023 |
| Technical specification |
Project Progress Status |
Project Progress Status |
| No Status Updated |
| Date of start of Package | Date is not specified |
|---|---|
| Scheduled date of Completion as per agreement | Date is not specified |
| Expected date of Completion | 30/06/2024 |
| TS Date | 25 Mar 2023 |
|---|
| Kozhikode Dist 1 Sn 3 - AE |
| Date: 23/07/2024 |
Work has been completed | 100% Completed
WORK COMPLETED ON 31.06.2024.
| Kozhikode PH Dn EE |
| Date: 20/04/2024 |
Work in progress | 80% Completed
Work in progress.