Jal Jeevan Mission (JJM)-Kodakara Grama Panchayath (Phase 1)- Feeder line from Vattekkad to Perambra and near hotel Varsha Kodakara to Marathampilly in Kodakara Grama panchayath-Pipeline Work

Project Jal Jeevan Mission (JJM)-Kodakara Grama Panchayath (Phase 1)- Feeder line from Vattekkad to Perambra and near hotel Varsha Kodakara to Marathampilly in Kodakara Grama panchayath-Pipeline Work
Project Code TCRJJM07203797P3
Type Package
Main Project Jal Jeevan Mission- Kodakara Grama Panchayath (Appendix 2) -Providing FHTC, Retrofitting and Augmentation of Existing Rural Water Supply Schemes
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description Jal Jeevan Mission (JJM)-Kodakara Grama Panchayath (Phase 1)- Feeder line from Vattekkad to Perambra and near hotel Varsha Kodakara to Marathampilly in Kodakara Grama panchayath-Pipeline Work
Status Completed
District Thrissur
Executing Office Chalakkudy PH Sn
Agreement Number
Agreement Date
TS Amount (Rs) 3100000
TS Number WRD/KWA-CE(CR)/EST_TS/12261/2023_26_1_1
Technical specification Feeder line from Vattekkad to Perambra and near hotel Varsha Kodakara to Marathampilly in Kodakara Grama panchayath

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 17/08/2023
Scheduled date of Completion as per agreement 15 Dec 2023
Expected date of Completion 16/02/2024

Processing Dates

TS Date 22 Jul 2023
Estimate Approval 22 Jul 2023
NIT Approval 22 Jul 2023
Tender Closing 08 Aug 2023
Technichal Pre-Qualification 08 Aug 2023
Price bid opening 09 Aug 2023

Approval Dates

Workorder Date 16 Aug 2023
NA 01 Sep 2023

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Chalakudy AE 1
Date: 26/06/2024

Work in progress | 82% Completed

GI Pipe line work completed.

Chalakudy AE 1
Date: 22/06/2024

Work in progress | 82% Completed

GI Pipe line work completed.