Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

WRD-005-126-PA-01-Project 12- ARWSS to Rajakkadu Rajakumari-Replacing balance length of 250 mm AC Gravity main with 250 mm DI K9 pipes from Kuruvila city to Kulapparackal

Project WRD-005-126-PA-01-Project 12- ARWSS to Rajakkadu Rajakumari-Replacing balance length of 250 mm AC Gravity main with 250 mm DI K9 pipes from Kuruvila city to Kulapparackal
Project Code IDKKIIFB01196084P3
Type Package
Main Project KIIFB-PROJECTS-TRAN2-WRD005-126-Replacement of Transmission mains in Muvattupuzha circle-ARWSS to Rajakkad-Rajakumary
Funding Agency KIIFB
Category KIIFB
Type of scheme Water Supply
Scheme KIIFB
Description Work includes replacement of damaged 250 mm AC with 250mm DI K9 pipe between km4/260 Kuruvilacity to 5/210 Kulaprachal
Status On-going
District Idukki
Executing Office Kattappana Project Dn
Agreement Number
Agreement Date
TS Amount (Rs)
TS Number
Technical specification Work includes replacement of damaged 250 mm AC with 250mm DI K9 pipe between km4/260 Kuruvilacity to 5/210 Kulaprachal

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 19/01/2019
Scheduled date of Completion as per agreement Date is not specified
Expected date of Completion 31/03/2023

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Kattapana Project Dn AE4
Date: 10/04/2023

Work has started | 0% Completed

The Technical Sanction estimate is under preparation in price 3.

Kattapana Project Dn AE4
Date: 03/04/2023

Work has started | 0% Completed

The Technical Sanction estimate is under preparation in price 3.