KIIFB-PROJECTS-TRAN2-WRD005-126-Replacement of Transmission mains in Muvattupuzha circle-ARWSS to Rajakkad-Rajakumary
Project |
KIIFB-PROJECTS-TRAN2-WRD005-126-Replacement of Transmission mains in Muvattupuzha circle-ARWSS to Rajakkad-Rajakumary |
Project Code |
IDKKIIFB01196084 |
Type |
Main project |
Funding Agency |
KIIFB |
Category |
KIIFB |
Type of scheme |
Water Supply |
Scheme |
KIIFB |
Description |
Replacing old and damaged AC/PVC pipes with DI K9 pipes |
Status |
On-going |
District |
Idukki |
Executing Office |
Thodupuzha PH Dn |
AS Amount (Rs) |
48677000
|
AS Number |
WRD005-126-PA-01 |
TS Amount (Rs) |
48677000 |
TS Number |
|
Total Bill Submitted (Rs) |
0 |
Total Bill Paid (Rs) |
0 |
Population Benefitted |
2000 |
Capacity in MLD |
2.00 |
Actual Project Completion Date |
Date is not specified |
Coverage |
Rajakumary |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
WRD-005-126-PA-01-Project 10- ARWSS to Rajakkadu Rajakumari-Replacing 250 mm AC Gravity main with 250 mm DI K9 pipes from the Kuruvila city to Rajakumari Tank |
Project Division Kattapana |
|
2 |
WRD005-126-PA-01-Project11-ARWSS to Rajakkadu Rajakumari-Replacing 250 mm AC Gravity main with 250 mm DI K9 pipes from Rajakumari Tank to parappanangadi tank |
Project Division Kattapana |
|
3 |
WRD-005-126-PA-01-Project 12- ARWSS to Rajakkadu Rajakumari-Replacing balance length of 250 mm AC Gravity main with 250 mm DI K9 pipes from Kuruvila city to Kulapparackal |
Project Division Kattapana |
|
4 |
WRD-005-126-PA-01-Project 13- ARWSS to Rajakkadu Rajakumari-Replacing 110mm PVC Gravity main with 100 mm DI K9 pipes from Kuruvila city to Kadukka city |
Project Division Kattapana |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
10 Apr 2023 |
The Technical Sanction estimate is under preparation in price 3 |
Kattapana Project Dn AE4 |
|
03 Apr 2023 |
The Technical Sanction estimate is under preparation in price 3 |
Kattapana Project Dn AE4 |
|
30 Mar 2023 |
The Technical Sanction estimate is under preparation in price 3 |
Kattapana Project Dn AE4 |
|
27 Mar 2023 |
The Technical Sanction estimate is under preparation in price 3 |
Kattapana Project Dn AE4 |
|
23 Mar 2023 |
The Technical Sanction estimate is under preparation in price 3 |
Kattapana Project Dn AE4 |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
19/01/2019 |
Scheduled date of Completion of the Project |
31 Dec 2022 |
Expected date of Completion |
31/03/2023 |