Project | Jal Jeevan Mission (JJM)-JJM : 5th SWSM : Providing 1027 fhtc`s in wards1,2,14 & 15 of Aruvappulam grama Panchayath by extension and replacing of pipelines. |
---|---|
Project Code | PTAJJM032214212P1 |
Type | Package |
Main Project | Jal Jeevan Mission (JJM)-JJM : 5th SWSM : Providing 1027 fhtc`s in wards1,2,14 & 15 of Aruvappulam grama Panchayath by extension and replacing of pipelines. |
Funding Agency | JJM |
Category | JJM |
Type of scheme | Water Supply |
Scheme | 4215-01-102-92-02 |
Description | Jal Jeevan Mission (JJM)-JJM : 5th SWSM : Providing 1027 fhtc`s in wards1,2,14 & 15 of Aruvappulam grama Panchayath by extension and replacing of pipelines. |
Status | On-going |
District | Pathanamthitta |
Executing Office | Konni Sn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 97900000 |
TS Number | TS/3971/2022_26_1_1 |
Technical specification | JJM : 5th SWSM : Providing 1027 fhtc`s in wards1,2,14 & 15 of Aruvappulam grama Panchayath by extension and replacing of pipelines. |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 31/03/2023 |
---|---|
Scheduled date of Completion as per agreement | 30 Sep 2023 |
Expected date of Completion | 30/09/2023 |
TS Date | 12 Nov 2022 |
---|---|
Estimate Approval | 12 Nov 2022 |
Tender Closing | 06 Dec 2022 |
Price bid opening | 08 Dec 2022 |
NA | 31 Mar 2023 |
---|
Konni PH Sn - AE |
Date: 26/06/2024 |
Work in progress | 92% Completed
FHTC : 461 Nos. 90 to 160mm PVC- 25.63 km , 80 to 150mm GI - 7.97km 150 mm to 200mm DI - 2.82 km.
Konni PH Sn - AE |
Date: 24/06/2024 |
Work in progress | 92% Completed
FHTC : 461 Nos. 90 to 160mm PVC- 25.63 km , 80 to 150mm GI - 7.97km 150 mm to 200mm DI - 2.82 km.