Jal Jeevan Mission (JJM)-JJM : 5th SWSM : Providing 1027 fhtc`s in wards1,2,14 & 15 of Aruvappulam grama Panchayath by extension and replacing of pipelines.

Project Jal Jeevan Mission (JJM)-JJM : 5th SWSM : Providing 1027 fhtc`s in wards1,2,14 & 15 of Aruvappulam grama Panchayath by extension and replacing of pipelines.
Project Code PTAJJM032214212
Type Main project
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description Jal Jeevan Mission (JJM)-JJM : 5th SWSM : Providing 1027 fhtc`s in wards1,2,14 & 15 of Aruvappulam grama Panchayath by extension and replacing of pipelines.
Status On-going
District Pathanamthitta
Executing Office Konni Sn
AS Amount (Rs) 135100000
AS Number G.O.(Rt)No.401/2022/WRD
TS Amount (Rs) 97900000
TS Number TS/3971/2022_26_1_1
Total Bill Submitted (Rs)
Total Bill Paid (Rs)
Population Benefitted
Capacity in MLD
Actual Project Completion Date Date is not specified
Coverage JJM : 5th SWSM : Providing 1027 fhtc`s in wards1,2,14 & 15 of Aruvappulam grama Panchayath by extension and replacing of pipelines.

Packages

No. Project Name Location View
1 Jal Jeevan Mission (JJM)-JJM : 5th SWSM : Providing 1027 fhtc`s in wards1,2,14 & 15 of Aruvappulam grama Panchayath by extension and replacing of pipelines. Konni Sn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
26 Jun 2024 FHTC : 461 Nos. 90 to 160mm PVC- 25.63 km , 80 to 150mm GI - 7.97km 150 mm to 200mm DI - 2.82 km Konni PH Sn - AE
24 Jun 2024 FHTC : 461 Nos. 90 to 160mm PVC- 25.63 km , 80 to 150mm GI - 7.97km 150 mm to 200mm DI - 2.82 km Konni PH Sn - AE
24 Jun 2024 FHTC : 461 Nos. 90 to 160mm PVC- 25.63 km , 80 to 150mm GI - 7.97km 150 mm to 200mm DI - 2.82 km Konni PH Sn - AE
16 May 2024 FHTC : 461 Nos. 90 to 160mm PVC- 25.8780 km , 80 to 150mm GI - 7.97km 150 mm to 200mm DI - 2.82 km Konni PH Sn - AE
23 Apr 2024 FHTC : 457 Nos. 90 to 160mm PVC- 25.820 km , 80 to 150mm GI - 7.97km 150 mm to 200mm DI - 2.82 km Konni PH Sn - AE

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 31/03/2023
Scheduled date of Completion of the Project 30 Sep 2023
Expected date of Completion 30/09/2023

Processing Dates

AS Date 13 May 2022
TS Date 12 Nov 2022

Other details

Project Officers View