KIIFB - Project WRD005-125- Replacement of Transmission Main Kochi PH circle - Project 18 Water supply to Kumbalam panchayath (CVC ready -mix plant to kumbalam south end)
KIIFB - Project WRD005-125- Replacement of Transmission Main Kochi PH circle - Project 18 Water supply to Kumbalam panchayath (CVC ready -mix plant to kumbalam south end)
Project Code
EKMKIIFB04217905
Type
Main project
Funding Agency
KIIFB
Category
KIIFB
Type of scheme
Water Supply
Scheme
KIIFB
Description
KIIFB - Project WRD005-125- Replacement of Transmission Main Kochi PH circle - Project 18 Water supply to Kumbalam panchayath (CVC ready -mix plant to kumbalam south end)
Status
Dropped
District
Ernakulam
Executing Office
Kochi Project Division
AS Amount (Rs)
29496814
AS Number
WRD005-125/APR-6/2021/KIIFB
TS Amount (Rs)
0
TS Number
Total Bill Submitted (Rs)
0
Total Bill Paid (Rs)
0
Population Benefitted
5000
Capacity in MLD
16.00
Actual Project Completion Date
Date is not specified
Coverage
Kumbalam panchayath
Packages
No.
Project Name
Location
View
1
KIIFB - Project WRD005-125- Replacement of Transmission Main Kochi PH circle - Project 18 Water supply to Kumbalam panchayath (CVC ready -mix plant to kumbalam south end)
Kochi Project Division
Overall Project Status
Status Date
Overall Project Status
Project Officer
Contact
06 Aug 2022
NHAI rejected the application for trenching. Insisted for duct or HDD. The Estimate revised within AS except NH duct provision. Additional 1000Lakhs required for duct provision. Proposal seems not financially viable.
Kochi JNURM Projects AE-6
01 Aug 2022
NHAI rejected the application for trenching. Insisted for duct or HDD.
The Estimate revised within AS except NH duct provision. Additional 1000Lakhs required for duct provision. Proposal seems not financially viable.
Kochi WS Project Dn EE
10 Jul 2022
It’s learned that open trench for pipe laying will not be permitted by NHAI. Meeting with NHAI is scheduled on 12.07.2022.
Kochi Jnnurm AE-3
30 Jun 2022
Joint site inspection conducted with NHAI on 16.06.2022
Kochi WS Project Dn AEE-2
22 Apr 2022
Site inspection done and estimate verification completed. For laying pipes along NHAI service road duct need to be constructed, Request given to NHAI. Need revised AS. Can be finalized after getting sanction from NHAI.