Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
06 Aug 2022 | NHAI rejected the application for trenching. Insisted for duct or HDD. The Estimate revised within AS except NH duct provision. Additional 1000Lakhs required for duct provision. Proposal seems not financially viable. | Kochi JNURM Projects AE-6 | |
01 Aug 2022 | NHAI rejected the application for trenching. Insisted for duct or HDD. The Estimate revised within AS except NH duct provision. Additional 1000Lakhs required for duct provision. Proposal seems not financially viable. | Kochi WS Project Dn EE | |
10 Jul 2022 | It’s learned that open trench for pipe laying will not be permitted by NHAI. Meeting with NHAI is scheduled on 12.07.2022. | Kochi Jnnurm AE-3 | |
30 Jun 2022 | Joint site inspection conducted with NHAI on 16.06.2022 | Kochi WS Project Dn AEE-2 | |
22 Apr 2022 | Site inspection done and estimate verification completed. For laying pipes along NHAI service road duct need to be constructed, Request given to NHAI. Need revised AS. Can be finalized after getting sanction from NHAI. | Kochi WS Project Dn AEE-2 | |
18 Apr 2022 | Site inspection done and estimate verification completed.For laying pipes along NHAI service road duct need to be constructed,Request given to NHAI. Need revised AS.Can be finalized after getting sanction from NHAI. | Kochi Jnnurm AE-3 | |
11 Feb 2022 | AS per Proceedings of SE, PH Circle , Kochi 11 No. PHC/CHN/A1/2846/2021 dtd. 10.01.2022, this work has to be transferred to Project Division Kochi 11 | Trippunithura WS Sn - AE 2 | |
02 Feb 2022 | AS per Proceedings of SE, PH Circle , Kochi 11 No. PHC/CHN/A1/2846/2021 dtd. 10.01.2022, this work has to be transferred to Project Division Kochi 11 | Kochi WS Dn EE | |
28 Jan 2022 | AS per Proceedings of SE, PH Circle , Kochi 11 No. PHC/CHN/A1/2846/2021 dtd. 10.01.2022, this work has to be transferred to Project Division Kochi 11 | Trippunithura WS Sn - AE 2 | |
22 Jan 2022 | AS per Proceedings of SE, PH Circle , Kochi 11 No. PHC/CHN/A1/2846/2021 dtd. 10.01.2022, this work has to be transferred to Project Division Kochi 11 | Trippunithura WS Sn - AE 2 |