- Home
- AMRUT-2.0-Supplying-laying -testing and...
AMRUT-2.0-Supplying-laying -testing and commissioning of Distribution system and providing FHTCs in Ponnani Municipality Phase-1.Pipe line work.
| Project |
AMRUT-2.0-Supplying-laying -testing and commissioning of Distribution system and providing FHTCs in Ponnani Municipality Phase-1.Pipe line work. |
| Project Code |
MLPAMRUT 2032314184 |
| Type |
Main project |
| Funding Agency |
AMRUT 2 |
| Category |
AMRUT 2 |
| Type of scheme |
Water Supply |
| Scheme |
|
| Description |
AMRUT-2.0-Supplying-laying -testing and commissioning of Distribution system and providing FHTCs in Ponnani Municipality Phase-1.Pipe line work |
| Status |
On-going |
| District |
Malappuram |
| Executing Office |
Edappal PH Dn |
| AS Amount (Rs) |
221500000
|
| AS Number |
G.O.(Rt)No.677/2023/LSGD |
| TS Amount (Rs) |
201200000 |
| TS Number |
WRD/KWA-CE(NR)/EST_TS/14483/2022_26_1_1 |
| Total Bill Submitted (Rs) |
|
| Total Bill Paid (Rs) |
|
| Population Benefitted |
25000 |
| Capacity in MLD |
50.00 |
| Actual Project Completion Date |
06 Jun 2025 |
| Coverage |
|
Packages
| No. |
Project Name |
Location |
View |
| 1 |
AMRUT-2.0-Supplying-laying -testing and commissioning of Distribution system and providing FHTCs in Ponnani Municipality Phase-1.Pipe line work. |
Ponnani Sn |
|
Overall Project Status
| Status Date |
Overall Project Status |
Project Officer |
Contact |
| 29 Aug 2025 |
Work in progress |
Edappal PH Dn EE |
|
| 25 Aug 2025 |
Work in progress |
Edappal PH Dn EE |
|
| 20 Aug 2025 |
Work in progress |
Edappal PH Dn EE |
|
| 27 Jun 2025 |
Work in progress |
Ponnani Sn AE |
|
| 23 Jun 2025 |
Work in progress |
Ponnani Sn AE |
|
No project review have been added to this project
Duration & Sanction dates
| Date of start of Project |
04/10/2023 |
| Scheduled date of Completion of the Project |
04 Oct 2023 |
| Expected date of Completion |
03/10/2024 |
Processing Dates
| AS Date |
21 Mar 2023 |
| TS Date |
20 May 2023 |