| Project | AMRUT-2.0-Supplying-laying -testing and commissioning of Distribution system and providing FHTCs in Ponnani Municipality Phase-1.Pipe line work. |
|---|---|
| Project Code | MLPAMRUT 2032314184P1 |
| Type | Package |
| Main Project | AMRUT-2.0-Supplying-laying -testing and commissioning of Distribution system and providing FHTCs in Ponnani Municipality Phase-1.Pipe line work. |
| Funding Agency | AMRUT 2 |
| Category | AMRUT 2 |
| Type of scheme | Water Supply |
| Scheme | |
| Description | AMRUT-2.0-Supplying-laying -testing and commissioning of Distribution system and providing FHTCs in Ponnani Municipality Phase-1.Pipe line work. |
| Status | On-going |
| District | Malappuram |
| Executing Office | Ponnani Sn |
| Agreement Number | |
| Agreement Date | |
| TS Amount (Rs) | 201200000 |
| TS Number | WRD/KWA-CE(NR)/EST_TS/14483/2022_26_1_1 |
| Technical specification |
Project Progress Status |
Project Progress Status |
| No Status Updated |
| Date of start of Package | 04/10/2023 |
|---|---|
| Scheduled date of Completion as per agreement | 03 Oct 2024 |
| Expected date of Completion | Date is not specified |
| TS Date | 20 May 2023 |
|---|---|
| Estimate Approval | 06 May 2023 |
| NIT Approval | 04 Oct 2023 |
| Tender Closing | 03 Jul 2023 |
| Technichal Pre-Qualification | 01 Jul 2023 |
| Price bid opening | 04 Jul 2023 |
| Workorder Date | 21 Sep 2023 |
|---|---|
| NA | 04 Oct 2023 |
| Ponnani Sn AE |
| Date: 08/10/2026 |
Work in progress | 93% Completed
Work in progress.
| Ponnani Sn AE |
| Date: 03/10/2026 |
Work in progress | 93% Completed
Work in progress.