Project | Jal Jeevan Mission- 2020-21- Phase I - Nattika Grama Panchayath- Providing FHTC to Rural house holds by augmentation of existing schemes and by ongoing schemes (MVS) |
---|---|
Project Code | TCRJJM08205244P1 |
Type | Package |
Main Project | Jal Jeevan Mission- 2020-21- Phase I - Nattika Grama Panchayath- Providing FHTC to Rural house holds by augmentation of existing schemes and by ongoing schemes (MVS) |
Funding Agency | JJM |
Category | JJM |
Type of scheme | Water Supply |
Scheme | 4215-01-102-92-02 |
Description | Jal Jeevan Mission- 2020-21- Phase I - Nattika Grama Panchayath- Providing FHTC to Rural house holds by augmentation of existing schemes and by ongoing schemes (MVS) - 2150 NOS |
Status | On-going |
District | Thrissur |
Executing Office | Vadanappalli Sn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 71630000 |
TS Number | TS/2020-2021/2020/21867 |
Technical specification | FHTC - 2150 NOS |
Contractor | THADATHIL MOHAMMED ALI (Mob: 9447733327) |
Issue date | Solved On | Action Taken On | Category | Description | Comments | Issue Status |
---|---|---|---|---|---|---|
10 Jun 2022 | Pending | Pending | Road Cut Related Risk | Application submitted to NH section for road cutting request. due to corrections they returned the application with adequate directions | No comments available. | Pending |
14 May 2021 | Pending | Pending | Road Cut Related Risk | ROW/107036/10138 - crossing at Nattika centre | No comments available. | Pending |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 22/10/2020 |
---|---|
Scheduled date of Completion as per agreement | 31 Mar 2021 |
Expected date of Completion | 31/03/2024 |
TS Date | 22 Oct 2020 |
---|---|
Estimate Approval | 22 Oct 2021 |
NIT Approval | 28 Oct 2020 |
Tender Closing | 04 Nov 2020 |
Technichal Pre-Qualification | 04 Nov 2020 |
Price bid opening | 04 Nov 2020 |
Workorder Date | 03 Dec 2020 |
---|---|
NA | 23 Mar 2021 |
Vadanappilly AE |
Date: 24/06/2024 |
Work has been completed | 100% Completed
1164 connections completed out of 2150(FHTC-804 and 360 htc) , 13th and Part bill submitted..
Vadanappilly AE |
Date: 27/04/2024 |
Work has been completed | 100% Completed
1164 connections completed out of 2150(FHTC-804 and 360 htc) , 13th and Part bill submitted..