Extension of period of completion
Extension of period of completion for JJM-Nattika-phase-1
CIPET certificate for JJM-Nattika-phase-1
CIPET certificate received
CIPET certificate for JJM-Nattika-phase-1
CIPET certificate received
CIPET certificate for JJM-Nattika-phase-1
CIPET certificate received
LETTER TO POLICE STATION
A letter has been sent to the police station asking for help in traffic control on the days when the work of laying pipes on roads where road cutting permission is granted.
NTK Time extension (Proposed date : 31-03-20123)
Request for time extension because of Rise in ground water level due to rain, shortage of 50mm PVC pipe with contractor and delay for sanctioning 50mm PVC pipe to contractor.