| Project | DRW 2022- CARWSS to Kulathupuzha and adjoining villages |
|---|---|
| Project Code | KLMGOK032210137P1 |
| Type | Package |
| Main Project | DRW 2022- CARWSS to Kulathupuzha and adjoining villages |
| Funding Agency | GOK |
| Category | DRW |
| Type of scheme | Water Supply |
| Scheme | 4215-01-800-89 |
| Description | DRW 2022- CARWSS to Kulathupuzha and adjoining villages - Raw Water Pump House Repair of 150 HP pump set and connected works |
| Status | On-going |
| District | Kollam |
| Executing Office | Madathara Sn |
| Agreement Number | |
| Agreement Date | |
| TS Amount (Rs) | 137177 |
| TS Number | TS/2022-2023/2022/13220 |
| Technical specification | DRW 2022- CARWSS to Kulathupuzha and adjoining villages - Raw Water Pump House Repair of 150 HP pump set and connected works |
Project Progress Status |
Project Progress Status |
| No Status Updated |
| Date of start of Package | 20/04/2022 |
|---|---|
| Scheduled date of Completion as per agreement | 05 May 2022 |
| Expected date of Completion | 05/05/2022 |
| TS Date | 13 Apr 2022 |
|---|---|
| Estimate Approval | 11 Apr 2022 |
| NIT Approval | 11 Apr 2022 |
| Tender Closing | 12 Apr 2022 |
| Technichal Pre-Qualification | 12 Apr 2022 |
| Price bid opening | 14 Apr 2022 |
| Workorder Date | 15 Apr 2022 |
|---|---|
| NA | 13 Apr 2022 |
| Madathara PH Sn - AE |
| Date: 30/05/2022 |
Work has been completed | 100% Completed
100% completed.
| Madathara PH Sn - AE |
| Date: 26/05/2022 |
Work in progress | 87% Completed
87% completed, work going on.