| Project | DRW 2022- CARWSS to Kulathupuzha and adjoining villages |
|---|---|
| Project Code | KLMGOK032210137 |
| Type | Main project |
| Funding Agency | GOK |
| Category | DRW |
| Type of scheme | Water Supply |
| Scheme | 4215-01-800-89 |
| Description | DRW 2022- CARWSS to Kulathupuzha and adjoining villages - Raw Water Pump House Repair of 150 HP pump set and connected works |
| Status | Completed |
| District | Kollam |
| Executing Office | Kadakkal PH Sub Dn |
| AS Amount (Rs) | 500000 |
| AS Number | 3476/AEII(OP)/2020/KWA(III) |
| TS Amount (Rs) | 459606 |
| TS Number | TS/2022-2023/2022/13220 |
| Total Bill Submitted (Rs) | 0 |
| Total Bill Paid (Rs) | 0 |
| Population Benefitted | 9000 |
| Capacity in MLD | 10.50 |
| Actual Project Completion Date | 05 May 2022 |
| Coverage | full coverage |
| Implementation Schedule | Download |
| Work Plan | Download |
| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 30 May 2022 | 100% completed | Madathara PH Sn - AE | |
| 26 May 2022 | 87% completed, work going on | Madathara PH Sn - AE | |
| 23 May 2022 | 85% completed, work going on | Madathara PH Sn - AE | |
| 19 May 2022 | 80% completed, work going on | Madathara PH Sn - AE | |
| 16 May 2022 | 78% completed, work going on | Madathara PH Sn - AE |
| Date of start of Project | 20/04/2022 |
|---|---|
| Scheduled date of Completion of the Project | 05 May 2022 |
| Expected date of Completion | 31/05/2022 |
| AS Date | 30 Mar 2022 |
|---|---|
| TS Date | 13 Apr 2022 |
| Project Officers | View |
|---|