Project | Jal Jeevan Mission-2020-21- Providing functional house hold Tap connections in Pulamanthole Grama Panchayath-Phase-2 |
---|---|
Project Code | MLPJJM12209080P1 |
Type | Package |
Main Project | Jal Jeevan Mission-2020-21 - Providing functional house hold Tap connections in Pulamanthole Grama Panchayath-Phase-2 |
Funding Agency | JJM |
Category | JJM |
Type of scheme | Water Supply |
Scheme | 4215-01-102-92-02 |
Description | Pipe Line Extension, FHTCs-4332 Pumpset |
Status | On-going |
District | Malappuram |
Executing Office | Perinthalmanna PH Sn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 149900000 |
TS Number | Reg .No. 13920/2021-2022 |
Technical specification | Pipe Line Extension, FHTCs-4332 Pumpset |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 18/02/2022 |
---|---|
Scheduled date of Completion as per agreement | 02 Nov 2022 |
Expected date of Completion | 30/09/2023 |
TS Date | 26 Nov 2021 |
---|---|
Estimate Approval | 26 Nov 2021 |
NIT Approval | 26 Nov 2022 |
Tender Closing | 21 Dec 2021 |
Technichal Pre-Qualification | 24 Dec 2021 |
Price bid opening | 24 Dec 2021 |
Workorder Date | 03 Feb 2022 |
---|---|
NA | 16 Feb 2022 |
Perinthalmanna AE |
Date: 28/06/2024 |
Work in progress | 60% Completed
899 FHTC &66 HTC given,Some HTC converted to FHTC, 9000m 250mm DI laid. 110mm HDPE 2500m laid. 90mm PE 14900.5m laid. 160mm HDPE 2800m laid .
Perinthalmanna AE |
Date: 15/06/2024 |
Work in progress | 60% Completed
843 FHTC &62 HTC given,Some HTC converted to FHTC, 9000m 250mm DI laid. 110mm HDPE 2500m laid. 90mm PE 14900.5m laid. 160mm HDPE 2800m laid .