Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

Budget -2017-2018-KIIFB project-TRAN10:WRD 025-13-WSS to Ramanchadi- Aligarh in Malappuram District- Package 3A- Electromechanical works

Project Budget -2017-2018-KIIFB project-TRAN10:WRD 025-13-WSS to Ramanchadi- Aligarh in Malappuram District- Package 3A- Electromechanical works
Project Code MLPKIIFB1118510P9
Type Package
Main Project Budget -2017-2018-KIIFB project-TRAN10:WRD 025-13-WSS to Ramanchadi- Aligarh in Malappuram District
Funding Agency KIIFB
Category KIIFB
Type of scheme Water Supply
Scheme KIIFB
Description This package includes 3 transformers (1 at WTP, 1 at well cum pump house and 1 at intermediate booster station), booster pumps, intermediate sump and Power line extension cables
Status On-going
District Malappuram
Executing Office Malappuram Project Dn
Agreement Number
Agreement Date
TS Amount (Rs) 57170000
TS Number TS/2021-2022/2021/16865
Technical specification 3 transformers (1 at WTP, 1 at well cum pump house and 1 at intermediate booster station), booster pumps, intermediate sump and Power line extension cables

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package Date is not specified
Scheduled date of Completion as per agreement 30 Nov 2023
Expected date of Completion 30/11/2023

Processing Dates

TS Date 12 Nov 2021
Estimate Approval 12 Nov 2021
NIT Approval 06 May 2022
Tender Closing 16 May 2022
Technichal Pre-Qualification 01 Jun 2022
Price bid opening 08 Jun 2022

Approval Dates

Workorder Date 28 Jun 2022

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Malappuram Project Dn AE3
Date: 03/05/2024

Work has started | 0% Completed

Design of pump set are completed and pump set order is placed by the contractor.630KVA and 160KVA Transformers supplied .

Malappuram Project Dn AE3
Date: 02/05/2024

Work has started | 0% Completed

Design of pump set are completed and pump set order is placed by the contractor.630KVA and 160KVA Transformers supplied .