| Project | Budget -2017-2018-KIIFB project-TRAN10:WRD 025-13-WSS to Ramanchadi- Aligarh in Malappuram District- Package 3A- Electromechanical works |
|---|---|
| Project Code | MLPKIIFB1118510P9 |
| Type | Package |
| Main Project | Budget -2017-2018-KIIFB project-TRAN10:WRD 025-13-WSS to Ramanchadi- Aligarh in Malappuram District |
| Funding Agency | KIIFB |
| Category | KIIFB |
| Type of scheme | Water Supply |
| Scheme | KIIFB |
| Description | This package includes 3 transformers (1 at WTP, 1 at well cum pump house and 1 at intermediate booster station), booster pumps, intermediate sump and Power line extension cables |
| Status | On-going |
| District | Malappuram |
| Executing Office | Malappuram Project Dn |
| Agreement Number | |
| Agreement Date | |
| TS Amount (Rs) | 57170000 |
| TS Number | TS/2021-2022/2021/16865 |
| Technical specification | 3 transformers (1 at WTP, 1 at well cum pump house and 1 at intermediate booster station), booster pumps, intermediate sump and Power line extension cables |
Project Progress Status |
Project Progress Status |
| No Status Updated |
| Date of start of Package | Date is not specified |
|---|---|
| Scheduled date of Completion as per agreement | 30 Nov 2023 |
| Expected date of Completion | 30/11/2023 |
| TS Date | 12 Nov 2021 |
|---|---|
| Estimate Approval | 12 Nov 2021 |
| NIT Approval | 06 May 2022 |
| Tender Closing | 16 May 2022 |
| Technichal Pre-Qualification | 01 Jun 2022 |
| Price bid opening | 08 Jun 2022 |
| Workorder Date | 28 Jun 2022 |
|---|
| Malappuram Project Dn AE3 |
| Date: 22/04/2026 |
Work in progress | 99% Completed
Work Completed. Final bill under preparations .
| Malappuram Project Dn AE3 |
| Date: 10/04/2026 |
Work in progress | 99% Completed
Work Completed. Final bill under preparations .