KIIFB-2016-17-WRD 002-09- Augmentation of WSS to Kottayam Municipality, Package V- Restoration of road damaged by laying pipelines along PWD Roads in Kottayam Municipal areas under PWD Roads Division, Kottayam
Project |
KIIFB-2016-17-WRD 002-09- Augmentation of WSS to Kottayam Municipality, Package V- Restoration of road damaged by laying pipelines along PWD Roads in Kottayam Municipal areas under PWD Roads Division, Kottayam |
Project Code |
KTMKIIFB0117545P6 |
Type |
Package |
Main Project |
KIIFB-2016-17- WRD-002-09 Augmentation of UWSS to Kottayam Municipality
|
Funding Agency |
KIIFB |
Category |
KIIFB |
Type of scheme |
Water Supply |
Scheme |
KIIFB |
Description |
This package involves the road restoration works on PWD roads which will be damaged while laying pipelines evisaged in Package 2 |
Status |
On-going |
District |
Kottayam |
Executing Office |
Kottayam Project Dn |
Agreement Number |
|
Agreement Date |
|
TS Amount (Rs) |
9350000 |
TS Number |
TS/2021-2022/2021/14225 |
Technical specification |
Restoration of roads to BM BC standards. |
Contractor |
Chicago Constructions International Pvt Ltd (Mob: 9447111906) |
No project review have been added to this project
Project Progress Status
|
Project Progress Status
|
Duration & Sanction dates
Date of start of Package |
28/09/2021 |
Scheduled date of Completion as per agreement |
30 Jun 2022 |
Expected date of Completion |
16/12/2022 |
Processing Dates
TS Date |
25 Jun 2021 |
Estimate Approval |
19 Jul 2021 |
NIT Approval |
19 Jul 2021 |
Tender Closing |
02 Aug 2021 |
Technichal Pre-Qualification |
04 Aug 2021 |
Price bid opening |
05 Aug 2021 |
Approval Dates
Workorder Date |
14 Sep 2021 |
NA |
28 Sep 2021 |
Other details
Project Schedule |
View |
Project Components |
View |
Project Officers |
View |
Kottayam Proj Dn AE4 |
Date: 16/04/2023 |
Work has been completed | 100% Completed
Road tarring works on all PWD roads damaged by pipelaying works and one Municipal road is completed now. No further works are pending.
.
Kottayam Proj Dn AE4 |
Date: 15/04/2023 |
Work has been completed | 100% Completed
Road tarring works on all PWD roads damaged by pipelaying works and one Municipal road is completed now. No further works are pending.
.