Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

JJM-2020-21- CWSS to Thenkara Grama Panchayath- Construction, commissioning and maintenance of 14 MLD WTP at Kanjirapuzha KWA compound, construction of raw water pump house, 15 LL OHSR at Anamooli, Supplying, laying, testing, commissioning and maintenance of 600 mm DI K9 Raw water Pumping main - 553 m , 300 m DI K9 clear water pumping main - 10291 m , supply and erection of RW and CW pumpset and 400KVA & 315KVA transformers

Project JJM-2020-21- CWSS to Thenkara Grama Panchayath- Construction, commissioning and maintenance of 14 MLD WTP at Kanjirapuzha KWA compound, construction of raw water pump house, 15 LL OHSR at Anamooli, Supplying, laying, testing, commissioning and maintenance of 600 mm DI K9 Raw water Pumping main - 553 m , 300 m DI K9 clear water pumping main - 10291 m , supply and erection of RW and CW pumpset and 400KVA & 315KVA transformers
Project Code PKDJJM07203310P1
Type Package
Main Project Jal Jeevan Mission- 20-21- CWSS to Thenkara, Thachampara, Kanjirapuzha and Karakurussi panchayaths- Phase II -Construction, commissioning and maintenance of 14 MLD WTP at Kanjirapuzha KWA compound, construction of raw water pump house, 15 LL OHSR at Anamooli, Supplying, laying, testing, commissioning and maintenance of Raw water Pumping main , clear water pumping main, supply and erection of RW and CW pumpset and 400KVA & 315KVA transformers
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description JJM-2020-21- CWSS to Thenkara Grama Panchayath- Construction, commissioning and maintenance of 14 MLD WTP at Kanjirapuzha KWA compound, construction of raw water pump house, 15 LL OHSR at Anamooli, Supplying, laying, testing, commissioning and maintenance of 600 mm DI K9 Raw water Pumping main - 553 m , 300 m DI K9 clear water pumping main - 10291 m , supply and erection of RW and CW pumpset and 400KVA & 315KVA transformers
Status On-going
District Palakkad
Executing Office Palakkad Project Dn
Agreement Number
Agreement Date
TS Amount (Rs) 215100000
TS Number TS/2021-2022/2022/2338
Technical specification Construction, commissioning and maintenance of 14 MLD WTP at Kanjirapuzha KWA compound, construction of raw water pump house, 15 LL OHSR at Anamooli, Supplying, laying, testing, commissioning and maintenance of 600 mm DI K9 Raw water Pumping main - 553 m , 300 m DI K9 clear water pumping main - 10291 m , supply and erection of RW and CW pumpset and 400KVA & 315KVA transformers
Contractor Binumathew (Mob: 9446462010)

No project review have been added to this project

Reported Issues

Issue date Solved On Action Taken On Category Description Comments Issue Status
30 Nov 2022 Pending Pending Technical Project Risk insufficent bearing capacity for identified land for 15LL OHSR at anamooli No comments available. Pending

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 29/06/2022
Scheduled date of Completion as per agreement 28 Dec 2023
Expected date of Completion 17/06/2024

Processing Dates

TS Date 03 Feb 2022
Estimate Approval 03 Feb 2022
NIT Approval 24 Mar 2022
Tender Closing 18 May 2022
Technichal Pre-Qualification 21 May 2022
Price bid opening 08 Jun 2022

Approval Dates

NA 12 Jul 2022
Workorder Date 29 Jun 2022

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Palakkad Proj AE 3
Date: 26/06/2024

Work in progress | 78% Completed

RW & CW pumping mains: DI pipes supplied, RW -600 mm DI & CW - 300 mm DI ,200 mm DI laying in progress.0.258 km RW & 8.31 km CW laid so far.Side wall maintenance work progressing Transformer work progressing.15LL Reservoir: Revised design from WASCON received and site clearance completed . WTP & allied works: Machanical work in progress. Clear water sump: All work are completed. Pump house & chlorine room above sump - structural work & painting completed. Filter house: Filter media filling, structural work completed. Handrail & painting work progressing, mechanical and electrical work on going. Aerator: structural work & plastering completed. Clarifier & Flocculator - hand rail work in progress, plate setter work , mechanical work on going. MCC Room: structural work & brick work completed. Chlorine gas tank fixed in plant..

Palakkad Proj AE 3
Date: 25/06/2024

Work in progress | 78% Completed

RW & CW pumping mains: DI pipes supplied, RW -600 mm DI & CW - 300 mm DI ,200 mm DI laying in progress.0.258 km RW & 8.31 km CW laid so far.Side wall maintenance work progressing Transformer work progressing.15LL Reservoir: Revised design from WASCON received and site clearance completed . WTP & allied works: Machanical work in progress. Clear water sump: All work are completed. Pump house & chlorine room above sump - structural work & painting completed. Filter house: Filter media filling, structural work completed. Handrail & painting work progressing, mechanical and electrical work on going. Aerator: structural work & plastering completed. Clarifier & Flocculator - hand rail work in progress, plate setter work , mechanical work on going. MCC Room: structural work & brick work completed. Chlorine gas tank fixed in plant..