JJM-2020-21- CWSS to Thenkara Grama Panchayath- Construction, commissioning and maintenance of 14 MLD WTP at Kanjirapuzha KWA compound, construction of raw water pump house, 15 LL OHSR at Anamooli, Supplying, laying, testing, commissioning and maintenance of 600 mm DI K9 Raw water Pumping main - 553 m , 300 m DI K9 clear water pumping main - 10291 m , supply and erection of RW and CW pumpset and 400KVA & 315KVA transformers
Project |
JJM-2020-21- CWSS to Thenkara Grama Panchayath- Construction, commissioning and maintenance of 14 MLD WTP at Kanjirapuzha KWA compound, construction of raw water pump house, 15 LL OHSR at Anamooli, Supplying, laying, testing, commissioning and maintenance of 600 mm DI K9 Raw water Pumping main - 553 m , 300 m DI K9 clear water pumping main - 10291 m , supply and erection of RW and CW pumpset and 400KVA & 315KVA transformers |
Project Code |
PKDJJM07203310P1 |
Type |
Package |
Main Project |
Jal Jeevan Mission- 20-21- CWSS to Thenkara, Thachampara, Kanjirapuzha and Karakurussi panchayaths- Phase II -Construction, commissioning and maintenance of 14 MLD WTP at Kanjirapuzha KWA compound, construction of raw water pump house, 15 LL OHSR at Anamooli, Supplying, laying, testing, commissioning and maintenance of Raw water Pumping main , clear water pumping main, supply and erection of RW and CW pumpset and 400KVA & 315KVA transformers
|
Funding Agency |
JJM |
Category |
JJM |
Type of scheme |
Water Supply |
Scheme |
4215-01-102-92-02 |
Description |
JJM-2020-21- CWSS to Thenkara Grama Panchayath- Construction, commissioning and maintenance of 14 MLD WTP at Kanjirapuzha KWA compound, construction of raw water pump house, 15 LL OHSR at Anamooli, Supplying, laying, testing, commissioning and maintenance of 600 mm DI K9 Raw water Pumping main - 553 m , 300 m DI K9 clear water pumping main - 10291 m , supply and erection of RW and CW pumpset and 400KVA & 315KVA transformers |
Status |
On-going |
District |
Palakkad |
Executing Office |
Palakkad Project Dn |
Agreement Number |
|
Agreement Date |
|
TS Amount (Rs) |
215100000 |
TS Number |
TS/2021-2022/2022/2338 |
Technical specification |
Construction, commissioning and maintenance of 14 MLD WTP at Kanjirapuzha KWA compound, construction of raw water pump house, 15 LL OHSR at Anamooli, Supplying, laying, testing, commissioning and maintenance of 600 mm DI K9 Raw water Pumping main - 553 m , 300 m DI K9 clear water pumping main - 10291 m , supply and erection of RW and CW pumpset and 400KVA & 315KVA transformers |
Contractor |
Binumathew (Mob: 9446462010) |
No project review have been added to this project
Reported Issues
Issue date |
Solved On |
Action Taken On |
Category |
Description |
Comments |
Issue Status |
30 Nov 2022 |
Pending |
Pending |
Technical Project Risk |
insufficent bearing capacity for identified land for 15LL OHSR at anamooli |
No comments available. |
Pending |
Project Progress Status
|
Project Progress Status
|
Duration & Sanction dates
Date of start of Package |
29/06/2022 |
Scheduled date of Completion as per agreement |
28 Dec 2023 |
Expected date of Completion |
17/06/2024 |
Processing Dates
TS Date |
03 Feb 2022 |
Estimate Approval |
03 Feb 2022 |
NIT Approval |
24 Mar 2022 |
Tender Closing |
18 May 2022 |
Technichal Pre-Qualification |
21 May 2022 |
Price bid opening |
08 Jun 2022 |
Approval Dates
NA |
12 Jul 2022 |
Workorder Date |
29 Jun 2022 |
Other details
Project Schedule |
View |
Project Components |
View |
Project Officers |
View |
Palakkad Proj AE 3 |
Date: 26/06/2024 |
Work in progress | 78% Completed
RW & CW pumping mains: DI pipes supplied, RW -600 mm DI & CW - 300 mm DI ,200 mm DI laying in progress.0.258 km RW & 8.31 km CW laid so far.Side wall maintenance work progressing Transformer work progressing.15LL Reservoir: Revised design from WASCON received and site clearance completed . WTP & allied works: Machanical work in progress. Clear water sump: All work are completed. Pump house & chlorine room above sump - structural work & painting completed. Filter house: Filter media filling, structural work completed. Handrail & painting work progressing, mechanical and electrical work on going. Aerator: structural work & plastering completed. Clarifier & Flocculator - hand rail work in progress, plate setter work , mechanical work on going. MCC Room: structural work & brick work completed. Chlorine gas tank fixed in plant..
Palakkad Proj AE 3 |
Date: 25/06/2024 |
Work in progress | 78% Completed
RW & CW pumping mains: DI pipes supplied, RW -600 mm DI & CW - 300 mm DI ,200 mm DI laying in progress.0.258 km RW & 8.31 km CW laid so far.Side wall maintenance work progressing Transformer work progressing.15LL Reservoir: Revised design from WASCON received and site clearance completed . WTP & allied works: Machanical work in progress. Clear water sump: All work are completed. Pump house & chlorine room above sump - structural work & painting completed. Filter house: Filter media filling, structural work completed. Handrail & painting work progressing, mechanical and electrical work on going. Aerator: structural work & plastering completed. Clarifier & Flocculator - hand rail work in progress, plate setter work , mechanical work on going. MCC Room: structural work & brick work completed. Chlorine gas tank fixed in plant..