Jal Jeevan Mission- 20-21- CWSS to Thenkara, Thachampara, Kanjirapuzha and Karakurussi panchayaths- Phase II -Construction, commissioning and maintenance of 14 MLD WTP at Kanjirapuzha KWA compound, construction of raw water pump house, 15 LL OHSR at Anamooli, Supplying, laying, testing, commissioning and maintenance of Raw water Pumping main , clear water pumping main, supply and erection of RW and CW pumpset and 400KVA & 315KVA transformers

Project Jal Jeevan Mission- 20-21- CWSS to Thenkara, Thachampara, Kanjirapuzha and Karakurussi panchayaths- Phase II -Construction, commissioning and maintenance of 14 MLD WTP at Kanjirapuzha KWA compound, construction of raw water pump house, 15 LL OHSR at Anamooli, Supplying, laying, testing, commissioning and maintenance of Raw water Pumping main , clear water pumping main, supply and erection of RW and CW pumpset and 400KVA & 315KVA transformers
Project Code PKDJJM07203310
Type Main project
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description Jal Jeevan Mission- 20-21- CWSS to Thenkara, Thachampara, Kanjirapuzha and Karakurussi panchayaths- Phase II -Construction, commissioning and maintenance of 14 MLD WTP at Kanjirapuzha KWA compound, construction of raw water pump house, 15 LL OHSR at Anamooli, Supplying, laying, testing, commissioning and maintenance of Raw water Pumping main , clear water pumping main, supply and erection of RW and CW pumpset and 400KVA & 315KVA transformers
Status On-going
District Palakkad
Executing Office Palakkad Project Dn
AS Amount (Rs) 515598000
AS Number G.O.(Rt)No.777/2020/WRD
TS Amount (Rs) 227250000
TS Number TS/2021-2022/2022/2338
Total Bill Submitted (Rs) 135975245
Total Bill Paid (Rs) 135975245
Population Benefitted 152669
Capacity in MLD 21.00
Actual Project Completion Date 17 Jun 2024
Coverage Thenkara, Kanjirappuzha, Karakkurissi and Thachampara Panchayaths
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 JJM-2020-21- CWSS to Thenkara Grama Panchayath- Construction, commissioning and maintenance of 14 MLD WTP at Kanjirapuzha KWA compound, construction of raw water pump house, 15 LL OHSR at Anamooli, Supplying, laying, testing, commissioning and maintenance of 600 mm DI K9 Raw water Pumping main - 553 m , 300 m DI K9 clear water pumping main - 10291 m , supply and erection of RW and CW pumpset and 400KVA & 315KVA transformers Project Division Palakkad

Overall Project Status

Status Date Overall Project Status Project Officer Contact
26 Jun 2024 RW & CW pumping mains: DI pipes supplied, RW -600 mm DI & CW - 300 mm DI ,200 mm DI laying in progress.0.258 km RW & 8.31 km CW laid so far.Side wall maintenance work progressing Transformer work progressing.15LL Reservoir: Revised design from WASCON received and site clearance completed . WTP & allied works: Machanical work in progress. Clear water sump: All work are completed. Pump house & chlorine room above sump - structural work & painting completed. Filter house: Filter media filling, structural work completed. Handrail & painting work progressing, mechanical and electrical work on going. Aerator: structural work & plastering completed. Clarifier & Flocculator - hand rail work in progress, plate setter work , mechanical work on going. MCC Room: structural work & brick work completed. Chlorine gas tank fixed in plant. Palakkad Proj AE 3
25 Jun 2024 RW & CW pumping mains: DI pipes supplied, RW -600 mm DI & CW - 300 mm DI ,200 mm DI laying in progress.0.258 km RW & 8.31 km CW laid so far.Side wall maintenance work progressing Transformer work progressing.15LL Reservoir: Revised design from WASCON received and site clearance completed . WTP & allied works: Machanical work in progress. Clear water sump: All work are completed. Pump house & chlorine room above sump - structural work & painting completed. Filter house: Filter media filling, structural work completed. Handrail & painting work progressing, mechanical and electrical work on going. Aerator: structural work & plastering completed. Clarifier & Flocculator - hand rail work in progress, plate setter work , mechanical work on going. MCC Room: structural work & brick work completed. Chlorine gas tank fixed in plant. Palakkad Proj AE 3
24 Jun 2024 RW & CW pumping mains: DI pipes supplied, RW -600 mm DI & CW - 300 mm DI ,200 mm DI laying in progress.0.258 km RW & 8.31 km CW laid so far.Side wall maintenance work progressing Transformer work progressing.15LL Reservoir: Revised design from WASCON received and site clearance completed . WTP & allied works: Machanical work in progress. Clear water sump: All work are completed. Pump house & chlorine room above sump - structural work & painting completed. Filter house: Filter media filling, structural work completed. Handrail & painting work progressing, mechanical and electrical work on going. Aerator: structural work & plastering completed. Clarifier & Flocculator - hand rail work in progress, plate setter work , mechanical work on going. MCC Room: structural work & brick work completed. Chlorine gas tank fixed in plant. Palakkad Proj AE 3
22 Jun 2024 RW & CW pumping mains: DI pipes supplied, RW -600 mm DI & CW - 300 mm DI ,200 mm DI laying in progress.0.258 km RW & 8.31 km CW laid so far.Side wall maintenance work progressing Transformer work progressing.15LL Reservoir: Revised design from WASCON received and site clearance completed . WTP & allied works: Machanical work in progress. Clear water sump: All work are completed. Pump house & chlorine room above sump - structural work & painting completed. Filter house: Filter media filling, structural work completed. Handrail & painting work progressing, mechanical and electrical work on going. Aerator: structural work & plastering completed. Clarifier & Flocculator - hand rail work in progress, plate setter work , mechanical work on going. MCC Room: structural work & brick work completed. Chlorine gas tank fixed in plant. Palakkad Proj AE 3
20 Jun 2024 RW & CW pumping mains: DI pipes supplied, RW -600 mm DI & CW - 300 mm DI ,200 mm DI laying in progress.0.258 km RW & 8.31 km CW laid so far.Side wall maintenance work progressing Transformer work progressing.15LL Reservoir: Revised design from WASCON received and site clearance completed . WTP & allied works: Machanical work in progress. Clear water sump: All work are completed. Pump house & chlorine room above sump - structural work & painting completed. Filter house: Filter media filling, structural work completed. Handrail & painting work progressing, mechanical and electrical work on going. Aerator: structural work & plastering completed. Clarifier & Flocculator - hand rail work in progress, plate setter work , mechanical work on going. MCC Room: structural work & brick work completed. Chlorine gas tank fixed in plant. Palakkad Proj AE 3

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 29/06/2022
Scheduled date of Completion of the Project 28 Dec 2023
Expected date of Completion 17/06/2024

Processing Dates

AS Date 24 Dec 2020
TS Date 03 Feb 2022