WSS TO KARUMALOOR & KUNNUKARA - PRODUCTION COMPONENTS

Project WSS TO KARUMALOOR & KUNNUKARA - PRODUCTION COMPONENTS
Project Code EKMKIIFB0619471P1
Type Package
Main Project KIIFB- WSS TO KARUMALOOR & KUNNUKARA PANCHAYATHS
Funding Agency KIIFB
Category KIIFB
Type of scheme Water Supply
Scheme KIIFB
Description Augmentation of WSS to Karumalloor and Kunnukara Panchayaths-Augmentation of WSS to Karumallur and Kunnukara Panchayaths - Phase I- Package II - Construction of 20 MLD WTP and allied works at Malayikkunnu in Kunnukara Panchayath, OHSR of Capacity 8.50LL at Malayikkunnu WTP Compound and Supply & erection of Pump sets.-General Civil Work
Status On-going
District Ernakulam
Executing Office Perumbavoor Project Dn
Agreement Number
Agreement Date
TS Amount (Rs) 207000000
TS Number WRD/KWA-CE(CR)/EST_TS/7924/2022_5_1_1
Technical specification Package 1 a) Land acquisition b) 9 m dia intake well cum pump house at Periyar, c)RWPS-65HP VT (2nos) d) CWPS- 35 HP CF (2 Nos), 25 HP CF (2 Nos), 25 HP CF (2 Nos) e) 200KVA Transformer at Raw water pump house f) 20MLD WTP, CWSump, PH and land improvement works at Malayikunnu site g) RWPM- 400 mm D1 K9 - 2007 m h)100KVA Transformer at Clear water pump house & WTP i) 8.5LL OHSR at Malayikunnu for Kunnukara j) 250 mm D1 K9 pipe - 60m & 150 mm D1 K9-100m to OHSRs at Malaikunnu in Kunnukara Panchayath.

No project review have been added to this project

Reported Issues

Issue date Solved On Action Taken On Category Description Comments Issue Status
17 Sep 2021 Pending Pending Land Related Risk Construction of production components - Well cum pump house, WTP, OHSR at Malayikunnu. - Private Land to be acquired for the construction of the above components. No comments available. Pending

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 18/06/2020
Scheduled date of Completion as per agreement Date is not specified
Expected date of Completion 31/08/2023

Processing Dates

TS Date 30 Jul 2023
Estimate Approval 30 Jul 2023

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Perumbavoor Project Dn AE2
Date: 27/04/2024

Work has started | 0% Completed

Due to some technical reasons, due extended to 06.05.2024 .

Perumbavoor Project Dn AE2
Date: 26/04/2024

Work has started | 0% Completed

Due to some technical reasons, due extended to 06.05.2024 .