KIIFB- WSS TO KARUMALOOR & KUNNUKARA PANCHAYATHS
Project |
KIIFB- WSS TO KARUMALOOR & KUNNUKARA PANCHAYATHS |
Project Code |
EKMKIIFB0619471 |
Type |
Main project |
Funding Agency |
KIIFB |
Category |
KIIFB |
Type of scheme |
Water Supply |
Scheme |
KIIFB |
Description |
KIIFB- Augmentation of water supply to Karumalloor and Kunnukara Panchayath
Package I & II |
Status |
On-going |
District |
Ernakulam |
Executing Office |
Perumbavoor Project Dn |
AS Amount (Rs) |
375000000
|
AS Number |
G.O.(Rt)No.85/2018/WRD |
TS Amount (Rs) |
0 |
TS Number |
Not issued |
Total Bill Submitted (Rs) |
30810105 |
Total Bill Paid (Rs) |
30810105 |
Population Benefitted |
71777 |
Capacity in MLD |
9.00 |
Actual Project Completion Date |
28 Dec 2022 |
Coverage |
Karumaloor & Kunnukara panchayaths |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
WSS TO KARUMALOOR & KUNNUKARA - PRODUCTION COMPONENTS |
Project Division Perumbavoor |
|
2 |
WSS TO KARUMALOOR & KUNNUKARA - PUMPING MAIN AND OHSRs |
Project Division Perumbavoor |
|
3 |
WSS TO KARUMALOOR & KUNNUKARA - WELL CUM PUMP HOUSE |
Project Division Perumbavoor |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
11 Jan 2024 |
KIIFB - Augmentation of WSS to Karumalloor and Kunnukara Panchayaths-Augmentation of WSS to Karumallur and Kunnukara Panchayaths - Phase I - Package I- FS received from KIIFB is less than AS amount, No final decision received from higher Office, Phase I - Package II- FS received from KIIFB is less than AS amount, No final decision received from higher Office, Phase I - Package III- FS received from KIIFB is less than AS amount, No final decision received from higher Office |
Perumbavoor Project Dn AE2 |
|
05 Jan 2024 |
KIIFB - Augmentation of WSS to Karumalloor and Kunnukara Panchayaths-Augmentation of WSS to Karumallur and Kunnukara Panchayaths - Phase I - Package I- FS received from KIIFB is less than AS amount, No final decision received from higher Office, Phase I - Package II- FS received from KIIFB is less than AS amount, No final decision received from higher Office, Phase I - Package III- FS received from KIIFB is less than AS amount, No final decision received from higher Office |
Perumbavoor Project Dn AE2 |
|
01 Jan 2024 |
KIIFB - Augmentation of WSS to Karumalloor and Kunnukara Panchayaths-Augmentation of WSS to Karumallur and Kunnukara Panchayaths - Phase I - Package I- FS received from KIIFB is less than AS amount, No final decision received from higher Office, Phase I - Package II- FS received from KIIFB is less than AS amount, No final decision received from higher Office, Phase I - Package III- FS received from KIIFB is less than AS amount, No final decision received from higher Office |
Perumbavoor Project Dn AE2 |
|
29 Dec 2023 |
KIIFB - Augmentation of WSS to Karumalloor and Kunnukara Panchayaths-Augmentation of WSS to Karumallur and Kunnukara Panchayaths - Phase I - Package I- FS received from KIIFB is less than AS amount, No final decision received from higher Office, Phase I - Package II- FS received from KIIFB is less than AS amount, No final decision received from higher Office, Phase I - Package III- FS received from KIIFB is less than AS amount, No final decision received from higher Office |
Perumbavoor Project Dn AE2 |
|
22 Dec 2023 |
KIIFB - Augmentation of WSS to Karumalloor and Kunnukara Panchayaths-Augmentation of WSS to Karumallur and Kunnukara Panchayaths - Phase I - Package I- FS received from KIIFB is less than AS amount, No final decision received from higher Office, Phase I - Package II- FS received from KIIFB is less than AS amount, No final decision received from higher Office, Phase I - Package III- FS received from KIIFB is less than AS amount, No final decision received from higher Office |
Perumbavoor Project Dn AE2 |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
Date is not specified |
Scheduled date of Completion of the Project |
28 Dec 2022 |
Expected date of Completion |
31/07/2025 |