KIIFB (TRAN2-WRD 005-130) - RENOVATION OF WSS TO PERAMBRA, KOOTHALI, CHAKKITTAPARA AND CHANGAROTH PANCHAYATHS

Project KIIFB (TRAN2-WRD 005-130) - RENOVATION OF WSS TO PERAMBRA, KOOTHALI, CHAKKITTAPARA AND CHANGAROTH PANCHAYATHS
Project Code CLTKIIFB03196093P1
Type Package
Main Project KIIFB Project – (TRAN2-WRD005-130):Replacement of Transmission Mains in Kozhikode Circle - Project 12–Renovation of WSS to Perambra, Koothali, Chakkittapara and ChangarothPanchayaths – Laying DI K9 Transmission main from Peruvannamuzhi Treatment Plant to Perambra GLSR
Funding Agency KIIFB
Category KIIFB
Type of scheme Water Supply
Scheme KIIFB
Description Supplying, Laying, Testing and commissioning of DI K9 pipes of diameter 600mm-1897m,500mm-7686m,450mm-4147m and 300mm-550m (total length of 14280m)as clear water gravity main from Peruvannamuzhi WTP to the GLSR at Chilambuvalavu for Perambra Panchayath and Supplying, Laying, Testing & Commissioning of 250mm DI K9 distribution main from Peruvannamuzhi WTP for Changaroth and koothali Panchayaths for a length of 5500m, with specials, Valves etc conforming to the relevant IS Specifications and Construction of valve chambers and anchor blocks wherever necessary.
Status On-going
District Kozhikkode
Executing Office Kozhikode Project Dn
Agreement Number
Agreement Date
TS Amount (Rs) 182200000
TS Number TS/12802/2020-21
Technical specification Supplying, Laying, Testing and commissioning of DI K9 pipes of diameter 600mm-1897m,500mm-7686m,450mm-4147m and 300mm-550m (total length of 14280m)as clear water gravity main from Peruvannamuzhi WTP to the GLSR at Chilambuvalavu for Perambra Panchayath and Supplying, Laying, Testing & Commissioning of 250mm DI K9 distribution main from Peruvannamuzhi WTP for Changaroth and koothali Panchayaths for a length of 5500m, with specials, Valves etc conforming to the relevant IS Specifications and Construction of valve chambers and anchor blocks wherever necessary.
Contractor Koya & Company Construction Limited (Mob: 9447885004)

No project review have been added to this project

Reported Issues

Issue date Solved On Action Taken On Category Description Comments Issue Status
13 Sep 2021 03 Jan 2022 Pending Road Cut Related Risk 1.Perambra-Kuttiyadi road from last Kallode to Varsha theatre-1000m 2. Perambra - Payyoli BM and BC road -1030m 3.Perambra-Cheruvannur BM and BC road-100m The KRFB agreed to issue road cutting permission after finalizing their road work bill from KIIFB. Hence MLA directed KRFB to issue permission as KWA is entrusted with reformation work in KIIFB projects. The issue is resolved Solved
07 Sep 2021 Pending Pending Road Cut Related Risk Road cutting permission need 1.Perambra- kuttiadi- koothali -375m (PWD). Solved Action Taken
07 Sep 2021 Pending Pending Road Cut Related Risk Road cutting permission to be obtained for 1.kallod to varsha theater along Perambra - kuttiyadi road. -500m (PWD). Solved Action Taken
07 Sep 2021 Pending Pending Road Cut Related Risk Road cutting permission to be obtained for 1.Perambra-Vadakara -230m (KRFB) Solved Action Taken

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 14/05/2021
Scheduled date of Completion as per agreement 04 Feb 2022
Expected date of Completion 28/02/2023

Processing Dates

TS Date 24 Dec 2020
Estimate Approval 24 Dec 2020
Tender Closing 25 Jan 2021
Price bid opening 05 Feb 2021

Approval Dates

Workorder Date 05 May 2021
NA 28 May 2021

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Kozhikode Project Dn AE5
Date: 28/02/2023

Work has been completed | 100% Completed

Work completed. .

Kozhikode Project Dn AE5
Date: 27/02/2023

Work in progress | 98% Completed

Pipe supplied- 1)500 mm DI -7683.5m, 2)250 mm DI - 5500 m , 3)600 mm DI -1914m, 4)300mmDI-552m, 5)450mm DI-4191m ,Total pipe supplied = 19841m. Pipe laid - 1)600mm-1848.95m, 2)500mm - 7335.77m ,3) 450mm -3881.7m, 4)250mm- 5500m, 5)300mm -498.75m, Total laid: 19065.17m, Laying work completed and Charging work completed. Road reformation work in progress. .