Project | KIIFB (TRAN2-WRD 005-130) - RENOVATION OF WSS TO PERAMBRA, KOOTHALI, CHAKKITTAPARA AND CHANGAROTH PANCHAYATHS |
---|---|
Project Code | CLTKIIFB03196093P1 |
Type | Package |
Main Project | KIIFB Project – (TRAN2-WRD005-130):Replacement of Transmission Mains in Kozhikode Circle - Project 12–Renovation of WSS to Perambra, Koothali, Chakkittapara and ChangarothPanchayaths – Laying DI K9 Transmission main from Peruvannamuzhi Treatment Plant to Perambra GLSR |
Funding Agency | KIIFB |
Category | KIIFB |
Type of scheme | Water Supply |
Scheme | KIIFB |
Description | Supplying, Laying, Testing and commissioning of DI K9 pipes of diameter 600mm-1897m,500mm-7686m,450mm-4147m and 300mm-550m (total length of 14280m)as clear water gravity main from Peruvannamuzhi WTP to the GLSR at Chilambuvalavu for Perambra Panchayath and Supplying, Laying, Testing & Commissioning of 250mm DI K9 distribution main from Peruvannamuzhi WTP for Changaroth and koothali Panchayaths for a length of 5500m, with specials, Valves etc conforming to the relevant IS Specifications and Construction of valve chambers and anchor blocks wherever necessary. |
Status | On-going |
District | Kozhikkode |
Executing Office | Kozhikode Project Dn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 182200000 |
TS Number | TS/12802/2020-21 |
Technical specification | Supplying, Laying, Testing and commissioning of DI K9 pipes of diameter 600mm-1897m,500mm-7686m,450mm-4147m and 300mm-550m (total length of 14280m)as clear water gravity main from Peruvannamuzhi WTP to the GLSR at Chilambuvalavu for Perambra Panchayath and Supplying, Laying, Testing & Commissioning of 250mm DI K9 distribution main from Peruvannamuzhi WTP for Changaroth and koothali Panchayaths for a length of 5500m, with specials, Valves etc conforming to the relevant IS Specifications and Construction of valve chambers and anchor blocks wherever necessary. |
Contractor | Koya & Company Construction Limited (Mob: 9447885004) |
Issue date | Solved On | Action Taken On | Category | Description | Comments | Issue Status |
---|---|---|---|---|---|---|
13 Sep 2021 | 03 Jan 2022 | Pending | Road Cut Related Risk | 1.Perambra-Kuttiyadi road from last Kallode to Varsha theatre-1000m 2. Perambra - Payyoli BM and BC road -1030m 3.Perambra-Cheruvannur BM and BC road-100m | The KRFB agreed to issue road cutting permission after finalizing their road work bill from KIIFB. Hence MLA directed KRFB to issue permission as KWA is entrusted with reformation work in KIIFB projects. The issue is resolved | Solved |
07 Sep 2021 | Pending | Pending | Road Cut Related Risk | Road cutting permission need 1.Perambra- kuttiadi- koothali -375m (PWD). | Solved | Action Taken |
07 Sep 2021 | Pending | Pending | Road Cut Related Risk | Road cutting permission to be obtained for 1.kallod to varsha theater along Perambra - kuttiyadi road. -500m (PWD). | Solved | Action Taken |
07 Sep 2021 | Pending | Pending | Road Cut Related Risk | Road cutting permission to be obtained for 1.Perambra-Vadakara -230m (KRFB) | Solved | Action Taken |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 14/05/2021 |
---|---|
Scheduled date of Completion as per agreement | 04 Feb 2022 |
Expected date of Completion | 28/02/2023 |
TS Date | 24 Dec 2020 |
---|---|
Estimate Approval | 24 Dec 2020 |
Tender Closing | 25 Jan 2021 |
Price bid opening | 05 Feb 2021 |
Workorder Date | 05 May 2021 |
---|---|
NA | 28 May 2021 |
Kozhikode Project Dn AE5 |
Date: 28/02/2023 |
Work has been completed | 100% Completed
Work completed. .
Kozhikode Project Dn AE5 |
Date: 27/02/2023 |
Work in progress | 98% Completed
Pipe supplied- 1)500 mm DI -7683.5m, 2)250 mm DI - 5500 m , 3)600 mm DI -1914m, 4)300mmDI-552m, 5)450mm DI-4191m ,Total pipe supplied = 19841m. Pipe laid - 1)600mm-1848.95m, 2)500mm - 7335.77m ,3) 450mm -3881.7m, 4)250mm- 5500m, 5)300mm -498.75m, Total laid: 19065.17m, Laying work completed and Charging work completed. Road reformation work in progress. .