KIIFB 2017-2018--CWSS to Vandazhy,Kizhakkenchery,vadakkenchery and kannambra panchayaths in palakkad district-Phase-II-Package-2-part-II

Project KIIFB 2017-2018--CWSS to Vandazhy,Kizhakkenchery,vadakkenchery and kannambra panchayaths in palakkad district-Phase-II-Package-2-part-II
Project Code PKDKIIFB1118631P3
Type Package
Main Project KIIFB -17-18 - Vandazhi, Kizhakkencherry, Vadakkencherry & Kannambra Comprehensive Fresh Water distribution project – Phase II in Palakkad District
Funding Agency KIIFB
Category KIIFB
Type of scheme Water Supply
Scheme KIIFB
Description Supplying and Laying of distribution network in Low level zone of Kannambra grama panchayat in Alathur Taluk from 22 LL OHSR at Karimkunnam - laying Transmission main after NH Crossing for Kannambra LL Zone 6
Status On-going
District Palakkad
Executing Office Chittur Project Dn
Agreement Number
Agreement Date
TS Amount (Rs) 115200000
TS Number ORDER No. TS/2021-2022/2020/5957
Technical specification Supplying and Laying of distribution network in Low level zone of Kannambra grama panchayat in Alathur Taluk from 22 LL OHSR at Karimkunnam - laying Transmission main after NH Crossing for Kannambra LL Zone 6

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 18/06/2020
Scheduled date of Completion as per agreement Date is not specified
Expected date of Completion 31/12/2023

Processing Dates

TS Date 24 May 2021
Estimate Approval 24 May 2021
NIT Approval 26 May 2021
Tender Closing 16 Jun 2021
Technichal Pre-Qualification 18 Jun 2021

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Chittur Project Dn - AE 3
Date: 23/04/2024

Work has started | 0% Completed

Work not started.

Chittur Project Dn - AE 3
Date: 11/04/2024

Work has started | 0% Completed

Work not started.