Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

KIIFB – 2017 - 2018- Jalagramam CWSS to kozhinjampara vadakarapathy and Eruthenpathy Panchayaths in Palakkad District - Phase- I- Package II - Design ,Construction commissioning and maintenance of 11.00 LL OHSR, at Ozhalapathy in vadakarapathy panchayath

Project KIIFB – 2017 - 2018- Jalagramam CWSS to kozhinjampara vadakarapathy and Eruthenpathy Panchayaths in Palakkad District - Phase- I- Package II - Design ,Construction commissioning and maintenance of 11.00 LL OHSR, at Ozhalapathy in vadakarapathy panchayath
Project Code PKDKIIFB1118675P2
Type Package
Main Project Jalagramam- CWSS to Kozhijampara, Vadakarapathy and Eruthenpathy Panchayaths in palakkad district -Phase I
Funding Agency KIIFB
Category KIIFB
Type of scheme Water Supply
Scheme KIIFB
Description KIIFB – 2017 - 2018- Jalagramam CWSS to kozhinjampara vadakarapathy and Eruthenpathy Panchayaths in Palakkad District - Phase- I- Package II - Design ,Construction commissioning and maintenance of 11.00 LL OHSR, at Ozhalapathy in vadakarapathy panchayath
Status On-going
District Palakkad
Executing Office Chittur Project Dn
Agreement Number
Agreement Date
TS Amount (Rs) 21000000
TS Number 2019-20/2019/18756,dated 13-12-2019
Technical specification Design ,Construction commissioning and maintenance of 11.00 LL OHSR, at Ozhalapathy in vadakarapathy panchayath
Contractor K.A.Abraham Managing partner J and B construction (Mob: 9447725266)

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 22/01/2020
Scheduled date of Completion as per agreement 21 Jan 2021
Expected date of Completion 31/03/2022

Processing Dates

TS Date 13 Dec 2019
Estimate Approval 13 Dec 2019
NIT Approval 13 Dec 2019
Tender Closing 21 Jan 2020
Technichal Pre-Qualification 18 Jan 2021
Price bid opening 21 Jan 2020

Approval Dates

Workorder Date 22 Jan 2020
NA 06 Feb 2020

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Chittur Project Dn - EE
Date: 23/08/2022

Work has been completed | 100% Completed

Work completed. Final Bill under preparation.

Chittur Project Dn - AE 4
Date: 30/03/2022

Work has been completed | 100% Completed

WORK COMPLETED ON 30.03.2022.