KIIFB – 2017 - 2018- Jalagramam CWSS to kozhinjampara vadakarapathy and Eruthenpathy Panchayaths in Palakkad District - Phase- I- Package II - Design ,Construction commissioning and maintenance of 11.00 LL OHSR, at Ozhalapathy in vadakarapathy panchayath
Project |
KIIFB – 2017 - 2018- Jalagramam CWSS to kozhinjampara vadakarapathy and Eruthenpathy Panchayaths in Palakkad District - Phase- I- Package II - Design ,Construction commissioning and maintenance of 11.00 LL OHSR, at Ozhalapathy in vadakarapathy panchayath |
Project Code |
PKDKIIFB1118675P2 |
Type |
Package |
Main Project |
Jalagramam- CWSS to Kozhijampara, Vadakarapathy and Eruthenpathy Panchayaths in palakkad district -Phase I
|
Funding Agency |
KIIFB |
Category |
KIIFB |
Type of scheme |
Water Supply |
Scheme |
KIIFB |
Description |
KIIFB – 2017 - 2018- Jalagramam CWSS to kozhinjampara vadakarapathy and Eruthenpathy Panchayaths in Palakkad District - Phase- I- Package II - Design ,Construction commissioning and maintenance of 11.00 LL OHSR, at Ozhalapathy in vadakarapathy panchayath |
Status |
On-going |
District |
Palakkad |
Executing Office |
Chittur Project Dn |
Agreement Number |
|
Agreement Date |
|
TS Amount (Rs) |
21000000 |
TS Number |
2019-20/2019/18756,dated 13-12-2019 |
Technical specification |
Design ,Construction commissioning and maintenance of 11.00 LL OHSR, at Ozhalapathy in vadakarapathy panchayath |
Contractor |
K.A.Abraham Managing partner J and B construction (Mob: 9447725266) |
No project review have been added to this project
Project Progress Status
|
Project Progress Status
|
Duration & Sanction dates
Date of start of Package |
22/01/2020 |
Scheduled date of Completion as per agreement |
21 Jan 2021 |
Expected date of Completion |
31/03/2022 |
Processing Dates
TS Date |
13 Dec 2019 |
Estimate Approval |
13 Dec 2019 |
NIT Approval |
13 Dec 2019 |
Tender Closing |
21 Jan 2020 |
Technichal Pre-Qualification |
18 Jan 2021 |
Price bid opening |
21 Jan 2020 |
Approval Dates
Workorder Date |
22 Jan 2020 |
NA |
06 Feb 2020 |
Other details
Project Schedule |
View |
Project Components |
View |
Project Officers |
View |
Chittur Project Dn - EE |
Date: 23/08/2022 |
Work has been completed | 100% Completed
Work completed. Final Bill under preparation.
Chittur Project Dn - AE 4 |
Date: 30/03/2022 |
Work has been completed | 100% Completed
WORK COMPLETED ON 30.03.2022.