Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

AMRUT-2.0-Replacement of old AC pipes and service connection shifting under WS Sub Dn,KOllam

Project AMRUT-2.0-Replacement of old AC pipes and service connection shifting under WS Sub Dn,KOllam
Project Code KLMAMRUT112518253
Type Main project
Funding Agency AMRUT
Category AMRUT 2
Type of scheme Water Supply
Scheme AMRUT
Description AMRUT-2.0-Replacement of old AC pipes and service connection shifting
Status On-going
District Kollam
Executing Office Kollam PH Dn
AS Amount (Rs) 55550000
AS Number G.O.(Rt)No.2764/2025/LSGD
TS Amount (Rs)
TS Number
Total Bill Submitted (Rs)
Total Bill Paid (Rs)
Population Benefitted
Capacity in MLD
Actual Project Completion Date Date is not specified
Coverage

Packages

No. Project Name Location View
1 AMRUT 2.0-Replacement of old AC pipes and service connection shifting at Vadakkevila, Eravipuram and Kilikolloor areas of Kollam Corporation under WSSn no. 3 Kollam- Kollam WS Sn 3
2 AMRUT 2.0- REPLACEMENT OF OLD AC PIPES AND SERVICE CONNECTION SHIFTING IN OLD MUNCIPAL AREAS OF KOLLAM MUNCIPAL CORPORATION Kollam WS Sn 1
3 AMRUT 2- Augmentation of QWSS-Replacement of old AC pipes and service connection shifting in various places of Sakthikulangara and Thrikkadavoor area of Kollam Corporation Kollam WS Sn 2
4 AMRUT-Asramam OHSR-Replacement of 250mm AC pipeline with 250mm DI pipe near Asramam OHSR Kollam PH Dn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
23 Oct 2026 Package 2- Work started and in progress- 10 % completed. package 1- Work completed and final bill submitted . Package 3- Site Handed over and pipe supplied. Package 4- Sakthikulangra& Thrikkadavoor area- AC plugging and alteration works in progressing- 70% completed. Kollam WS Sn 2 - AE
15 Oct 2026 Package 2- Work started and in progress- 10 % completed. package 1- Work completed and final bill submitted . Package 3- Site Handed over and pipe supplied. Package 4- Sakthikulangra& Thrikkadavoor area- Pipe laying work and alteration works in progressing- 65% completed. Kollam WS Sn 2 - AE
06 Oct 2026 Package 1- Work started and in progress- 1 % completed. package 2- Work completed and final bill submitted Package 3- Site Handed over. Package 4- Sakthikulangra& Thrikkadavoor area- Pipe laying work and alteration works in progressing- 60% completed. Kollam WS Sn 2 - AE
01 Oct 2026 Package 1- Work started and in progress- 1 % completed. package 2- Work completed and final bill submitted Package 3- Site Handed over. Package 4- Sakthikulangra& Thrikkadavoor area- Pipe laying work in progressing- 60% completed. Kollam WS Sn 2 - AE
23 Sep 2026 Package 1- Work started and in progress- 1 % completed. package 2- Work completed and final bill submitted Package 3- Agreement execution under process. Package 4- Sakthikulangra& Thrikkadavoor area- Pipe laying work in progressing- 60% completed. Kollam WS Sn 2 - AE

No project review have been added to this project

Duration & Sanction dates

Date of start of Project Date is not specified
Scheduled date of Completion of the Project Date is not specified
Expected date of Completion Date is not specified

Processing Dates

AS Date 10 Nov 2025

Other details

Project Officers View